Total quantity or scope of tender
The compressed air plant project is a significant part of a major project to design, construct and commission a milk processing plant at the Haverfordwest site, and will be delivered in conjunction with other major works on site but splits into seven distinct phases with some of the work being carried out directly by the Purchaser and some work by the supplier, as follows:
Phase 1
The Purchaser (contractor TBA) will be excavating the project area and constructing new buildings, concrete plinths, ducts and drains, and pathways to provide support and housing for all new equipment.
Phase 2
The Purchaser (contractor TBA) will erect a low voltage power distribution building, provide power supply to the plant, and install new compressed air main.
Phase 3
The Supplier will supply, offload, and install compressed air plant and associated equipment.
Phase 4
The Purchaser (contractor TBA) will supply and install new electrical feed cables and compressed air main.
Phase 5
The Supplier will install electrical power distribution from their distribution panel to meet all their requirements, and install interconnecting compressed air and drain pipework within Compressor Room.
Phase 6
The Supplier will install all safety equipment to enable full operation of plant.
Phase 7
The Purchaser (contractor TBA) will complete supply and installation of all distribution pipework external to Air Compressor Room.
The works will be carried out as part of a Notified CDM project.
The full specification is available, upon request, for interested parties in order to tender accurately.
|