Project Manager & Quantity Surveyor, Cyfarthfa Castle

  • First published: 15 January 2024
  • Last modified: 15 January 2024
  • Version: N/A
  • This file may not be fully accessible.

  •  

Information icon
You are viewing an expired notice.

Contents

Summary

OCID:
ocds-kuma6s-138050
Published by:
The Cyfarthfa Foundation
Authority ID:
AA84302
Publication date:
15 January 2024
Deadline date:
19 February 2024
Notice type:
Contract Notice
Has documents:
Yes
Has SPD:
No
Has Carbon Reduction Plan:
No

Abstract

Overview The Foundation require a suitably qualified Project Manager & Quantity Surveyor to progress the scheme onto a rounded RIBA 1 such that it can be presented to the National Lottery Heritage Fund and other funders as part of a coordinated and compelling application for development funding in order to progress. In the first instance, the appointment is only for Project Manager & Quantity Surveyor services up to RIBA 1. Services thereafter will be subject to further competitive procurement to meet funder requirements; it is anticipated that Project Manager & Quantity Surveyor services for RIBA 2 – 7 inclusive will be tendered in line with public procurement requirements with a break clause at the end of RIBA 3 where the contract will be renewed subject to funding and satisfactory performance. The Project Manager & Quantity Surveyor are required to support the development of the project up to the preparation of a National Lottery Heritage Fund (NLHF) Development Stage bid targeted for submission in August 2025. The Project Manager will be required to arrange the appointment of the Design Team (separately tendered) and to coordinate their work, and the work of any other consultants appointed, such that there is a coherent, comprehensive and compelling project developed to RIBA 1 level of detail ready for August 2025. The Quantity Surveyor will be required to review costings to date, advise on the cost implications of any variations, and to prepare a RIBA 1 Cost Estimate for inclusion in the Development Stage bid. The brief therefore requires timely and effective working within a relatively short period of time including assimilating previous outline proposals and information such that the overall proposal remains in line with anticipated requirements and scale, whilst taking the opportunity to consider this in conjunction with the client and professional team. The existing information is as follows: Document Author For Date Conservation Management Plan The Conservation Studio, rev MTCBC MTCBC 2009, rev Jan 2019 Cyfarthfa Plan Ian Ritchie MTCBC August 2019 Condition Survey Purcell MTCBC August 2022 Condition Survey - Cost Plan Synergy MTCBC August 2022 Inception Project – Stage 1 Report Counterculture Cyfarthfa Foundation April 2023 Cyfarthfa Masterplan–Landscape Appraisal Grant Associates Cyfarthfa Foundation April 2023 Order of Cost Estimate Turner & Townsend NCAGW May 2023 NGCAW Bid Cyfarthfa Foundation/Cultural Assocs NCAGW 2023 Inception Project–Final Report Counterculture Cyfarthfa Foundation August 2023 In addition to the documents shown above, there is a Project Execution Plan and appendices including Risk Register, programme, and budget/cashflow template. The information is supplied as a Wetransfer link for consideration when preparing a response to this brief. Skills and Experience Required • Experience of working on major Heritage Fund schemes • Experience of working on heritage sites of considerable significance including those listed at Grade I and preferably in the context of registered parks & gardens • Experience of working with 19th century buildings and structures • Ability to work collaboratively in a timely way, assimilating a wide range of information such that it can incorporated into a coherent and compelling vision • Experience of working with charitable organisations and reporting to a Board of Trustees • Experience of working within Wales on relevant projects and an appreciation for Welsh culture and heritage Scope of Work • Finalise the appointment of the Desig

Full notice text

CONTRACT NOTICE – NATIONAL

SERVICES

1 Authority Details

1.1

Authority Name and Address


The Cyfarthfa Foundation

The Bothy, Cyfarthfa Park,

Merthyr Tydfil

CF48 8RE

UK

Anna Baker

+44 7709776271

Finance@cyfarthfafoundation.wales

https://cyfarthfafoundation.wales/
https://www.sell2wales.gov.wales

1.2

Address from which documentation may be obtained


The Cyfarthfa Foundation

The Bothy, Cyfarthfa Park,

Merthyr Tydfil

CF48 8RE

UK

Anna Baker

+44 7709776271

Finance@cyfarthfafoundation.wales

https://cyfarthfafoundation.wales/

1.3

Completed documents must be returned to:


The Cyfarthfa Foundation

The Bothy, Cyfarthfa Park,

Merthyr Tydfil

CF48 8RE

UK

Anna Baker

+44 7709776271

Finance@cyfarthfafoundation.wales

https://cyfarthfafoundation.wales/

2 Contract Details

2.1

Title

Project Manager & Quantity Surveyor, Cyfarthfa Castle

2.2

Description of the goods or services required

Overview

The Foundation require a suitably qualified Project Manager & Quantity Surveyor to progress the scheme onto a rounded RIBA 1 such that it can be presented to the National Lottery Heritage Fund and other funders as part of a coordinated and compelling application for development funding in order to progress. In the first instance, the appointment is only for Project Manager & Quantity Surveyor services up to RIBA 1. Services thereafter will be subject to further competitive procurement to meet funder requirements; it is anticipated that Project Manager & Quantity Surveyor services for RIBA 2 – 7 inclusive will be tendered in line with public procurement requirements with a break clause at the end of RIBA 3 where the contract will be renewed subject to funding and satisfactory performance.

The Project Manager & Quantity Surveyor are required to support the development of the project up to the preparation of a National Lottery Heritage Fund (NLHF) Development Stage bid targeted for submission in August 2025. The Project Manager will be required to arrange the appointment of the Design Team (separately tendered) and to coordinate their work, and the work of any other consultants appointed, such that there is a coherent, comprehensive and compelling project developed to RIBA 1 level of detail ready for August 2025. The Quantity Surveyor will be required to review costings to date, advise on the cost implications of any variations, and to prepare a RIBA 1 Cost Estimate for inclusion in the Development Stage bid.

The brief therefore requires timely and effective working within a relatively short period of time including assimilating previous outline proposals and information such that the overall proposal remains in line with anticipated requirements and scale, whilst taking the opportunity to consider this in conjunction with the client and professional team. The existing information is as follows:

Document Author For Date

Conservation Management Plan The Conservation Studio, rev MTCBC MTCBC 2009, rev Jan 2019

Cyfarthfa Plan Ian Ritchie MTCBC August 2019

Condition Survey Purcell MTCBC August 2022

Condition Survey - Cost Plan Synergy MTCBC August 2022

Inception Project – Stage 1 Report Counterculture Cyfarthfa Foundation April 2023

Cyfarthfa Masterplan–Landscape Appraisal Grant Associates Cyfarthfa Foundation April 2023

Order of Cost Estimate Turner & Townsend NCAGW May 2023

NGCAW Bid Cyfarthfa Foundation/Cultural Assocs NCAGW 2023

Inception Project–Final Report Counterculture Cyfarthfa Foundation August 2023

In addition to the documents shown above, there is a Project Execution Plan and appendices including Risk Register, programme, and budget/cashflow template.

The information is supplied as a Wetransfer link for consideration when preparing a response to this brief.

Skills and Experience Required

• Experience of working on major Heritage Fund schemes

• Experience of working on heritage sites of considerable significance including those listed at Grade I and preferably in the context of registered parks & gardens

• Experience of working with 19th century buildings and structures

• Ability to work collaboratively in a timely way, assimilating a wide range of information such that it can incorporated into a coherent and compelling vision

• Experience of working with charitable organisations and reporting to a Board of Trustees

• Experience of working within Wales on relevant projects and an appreciation for Welsh culture and heritage

Scope of Work

• Finalise the appointment of the Design Team;

• Review the requirements for any external assistance in preparing the interpretation and activity plans, business planning, and evaluation, preparing briefs where these are required and procuring the same;

• Manage and coordinate the production of all the elements required to prepare a Heritage Fund Development Stage bid for submission in August 2024;

• Set up and manage a meeting and communications schedule for the period up to the submission of the Heritage Fund bid;

• Update the Project Execution Plan, including its appendices (i.e. budget/ cashflow, programme, and risk register) such that is can be supplied with the Development Stage bid as necessary;

• Manage the design team such that a coherent outline scheme is prepared as the basis of the Heritage Fund application;

• Review capital costs at RIBA 1 to ensure that there is adequate provision for these (including inflation) within the Heritage Fund bid;

• Prepare the Heritage Fund application form via the portal for client approval and submission;

• With the client, seek and incorporate advice from the Heritage Fund to ensure that the completed application is as competitive as possible;

• Support client fundraising with project detail as required and advise on potential sources of funding.

Timetable

The timetable for the project as a whole is anticipated as follows:

19th January 2024 Board of Trustees Approve PEP and Appendices

Mar – May 2024 Preparation & Submission of National Lottery Heritage Fund (NLHF) Expression of Interest

Mar - Apr 2024 Procurement of Professional Team to RIBA 1

Apr – Aug 2024 Preparation of outline documentation (drawings/ costings/ activity/ interpretation) to RIBA 1

Aug 2024 National Lottery Heritage Fund Development application submission

Dec 2024 National Lottery Heritage Fund Development award

Feb – Sep 2025 Procurement of Professional Team to RIBA 6 (with break clause after RIBA 3)

Apr – Dec 2025 Preparation of RIBA 2 documentation

Dec 2025 National Lottery Heritage Fund mid-stage review

Jan – Apr 2026 Preparation of RIBA 3 documentation

May 2026 National Lottery Heritage Fund Delivery application submission

May 2026 Submission of Planning & Listed Building Consent applications

Sep 2026 National Lottery Heritage Fund Delivery decision

Nov 2026 – Oct 2027 Preparation of detailed (RIBA 4) design and procurement of Principal Contractor

Oct 2027 – Sep 2029 Works on Site

Nov 2029 Grand Opening

It will therefore be noted that this is a relatively tight timescale, which requires effective, collaborative, and timely working across the professional team if it is to be met.

Fee

The maximum fee available is £30,000, including expenses and travel but excluding VAT.

Please note that if you feel that this does not cover the resource required to deliver against this brief, you are invited to state this in your submission. As such, a fee proposal of more than £30,000 does not automatically preclude consideration of a bid.

NOTE: To register your interest in this notice and obtain any additional information please visit the Sell2Wales Web Site at https://www.sell2wales.gov.wales/Search/Search_Switch.aspx?ID=138050.

2.3

Notice Coding and Classification

71240000 Architectural, engineering and planning services
71242000 Project and design preparation, estimation of costs
71244000 Calculation of costs, monitoring of costs
71246000 Determining and listing of quantities in construction
1015 Central Valleys (Merthyr Tydfil, Rhondda Cynon Taf)

2.4

Total quantity or scope of tender

Contract values £30,000 + VAT (including expenses and travel)

3 Conditions for Participation

3.1

Minimum standards and qualification required

4 Administrative Information

4.1

Type of Procedure

Single stage

4.2

Reference number attributed to the notice by the contracting authority

N/a

4.3

Time Limits

Time-limit for receipt of completed tenders
    19-02-2024  Time  12:00

Estimated award date
 04-03-2024

4.5

Language or languages in which tenders or requests to participate can be drawn up

EN 

4.6

Tender Submission Postbox

5 Other Information

5.1

Additional Information

(WA Ref:138050)

5.2

Additional Documentation

24 01 11 Cyfarthfa Castle - Project Manager & Quantity Surveyor

5.3

Publication date of this notice

 15-01-2024

Coding

Commodity categories

ID Title Parent category
71240000 Architectural, engineering and planning services Architectural and related services
71244000 Calculation of costs, monitoring of costs Architectural, engineering and planning services
71246000 Determining and listing of quantities in construction Architectural, engineering and planning services
71242000 Project and design preparation, estimation of costs Architectural, engineering and planning services

Delivery locations

ID Description
1015 Central Valleys (Merthyr Tydfil, Rhondda Cynon Taf)

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

Document family

Notice details
Publication date:
15 January 2024
Deadline date:
19 February 2024 00:00
Notice type:
Contract Notice
Authority name:
The Cyfarthfa Foundation
Publication date:
14 March 2024
Notice type:
Contract Award Notice
Authority name:
The Cyfarthfa Foundation

About the buyer

Main contact:
Finance@cyfarthfafoundation.wales
Admin contact:
Finance@cyfarthfafoundation.wales
Technical contact:
N/a
Other contact:
Finance@cyfarthfafoundation.wales

Further information

Date Details
22/01/2024 12:38
REPLACED FILE: 24 01 11 Cyfarthfa Castle - Project Manager & Quantity Surveyor
Invitation to Tender
22/01/2024 13:09
24 01 11 Cyfarthfa Castle - Project Manager Quantity Surveyor v2
Invitation to Tender - REPLACED FILE: 240111~2
24/01/2024 10:58
ADDED FILE: Query received by email
Question & Answer
07/02/2024 14:19
ADDED FILE: Question & answer (2)
Question received by email & response

Q&A

Ask the buyer any questions you may have relating to this notice. To ask the buyer a question or questions please click the "View Questions and Answers" button.

Additional documents

The following additional documents have been attached to this notice. To obtain these documents please select the individual file names below.

Current documents

DOC
DOC23.98 KB
This file may not be accessible.
DOC
DOC18.37 KB
This file may not be accessible.
DOC
DOC354.78 KB
This file may not be accessible.

Replaced documents

DOC
354.78 KB

0800 222 9004

Lines are open 8:30am to 5pm Monday to Friday.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.