CONTRACT NOTICE – OFFICIAL JOURNAL
|
Section I: Contracting Authority
|
I.1)
|
Name, Address and Contact Point(s)
|
|
Beaumont School |
Oakwood Drive |
St Albans |
AL4 0XB |
UK |
Procurement Consultant
Craig Pullen |
+44 1993700478 |
craig@cpconsulting.org.uk |
|
http://www.beaumontschool.com
|
|
|
|

 |
|

 |
|

 |
|
I.2)
|
Type of contracting Authority and Main Activity or Activities
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
|
|
No |
Section II: Object of the Contract
|
II.1)
|
Description
|
II.1.1)
|
Title attributed to the contract by the contracting authorityProvision of Construction Works for sports hall and other teaching accommodation at Beaumont School plus sub ground storm water drainage works on the school campus. |
II.1.2(a))
|
Type of works contract
|
II.1.2(b))
|
Type of supplies contract
|
II.1.2(c))
|
Type of service contract
|
II.1.2)
|
Main site or location of works, place of delivery or performance
Beaumont School, Oakwood Drive, St Albans, AL4 0XB.
UKH23 |
II.1.3)
|
This notice involves
|
 |
|
 |
|
 |
|
II.1.4)
|
Information on framework agreement (if applicable)
|
 |
|
 |
|
|
Number of participants to the framework agreement envisaged
|
|
Duration of the framework agreement
|
|
Justification for a framework agreement the duration of which exceeds four years
|
|
Estimated total value of purchases for the entire duration of the framework agreement
|
|
Frequency and value of the contracts to be awarded |
II.1.5)
|
Short description of the contract or purchase(s)
JCT With Contractors Design.
|
II.1.6)
|
Common Procurement Vocabulary (CPV)
|
|
|
|
45214200 |
|
|
|
|
|
II.1.7)
|
Contract covered by the Government Procurement Agreement (GPA) |
II.1.8)
|
Division into lots No |
II.1.9)
|
Will variants be accepted
No |
II.2)
|
Quantity or Scope of the Contract
|
II.2.1)
|
Total quantity or scopeA single contractor will be appointed to carry out the proposed work noted in ii.1.5 on the basis of a design and construction procurement route. |
|
6 900 000 GBP |
II.2.2)
|
Options |
|
Provisional timetable for recourse to these options
|
|
Number of possible renewals
|
|
In the case of renewable supplies or service contracts, estimated time frame for subsequent contracts
|
II.3)
|
Duration of the contract or limit for completion12 |
Section III: Legal, Economic, Financial and Technical Information
|
III.1)
|
Conditions Relating to the Contract
|
III.1.1)
|
Deposits and guarantees required
Bond not required — parent company guarantee may be required.
|
III.1.2)
|
Main Terms of financing and payment and/or reference to the relevant provisions
Sports hall works fully funded via receipts from Hertfordshire County Council from the sale of the current school playing fields. Drainage works fully funded via EFA grant.
|
III.1.3)
|
Legal form to be taken by the grouping of suppliers, contractors or service providers to whom the contract is to be awarded
Details to be set out within the contract tender documents.
|
III.1.4)
|
Other particular conditions to which the performance of the contract is subject
As set out in the invitation to tender, associated documents and in the form of contract.
|
III.2)
|
Conditions for Participation
|
III.2.1)
|
Personal situation of economic operators, including requirements relating to enrolment on professional or trade registers
Register the project under the CCS scheme.
Key site personnel will be subject to DBS checks.
|
III.2.2)
|
Economic and financial capacity
As set out in the Pre-Qualification Questionnaire and supporting documentation.
|
III.2.3)
|
Technical capacity
As set out in the Pre-Qualification Questionnaire and supporting documentation.
|
III.2.4)
|
Reserved contracts
|
 |
|
 |
|
Section IV: Procedure
|
IV.1)
|
Type of Procedure
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
Justification for the choice of accelerated procedure
|
IV.1.1)
|
Have candidates already been selected? No |
IV.1.2)
|
Limitations on the number of operators who will be invited to tender or to participate35 |
|
|
Objective criteria for choosing the limited number of candidates
|
IV.1.3)
|
Reduction of the number of operators during the negotiation or dialogue
|
 |
|
IV.2)
|
Award Criteria
|
|
No
|
|
|
|
Yes
|
|
No
|
IV.2.2)
|
An electronic auction will be used No
|
IV.3 Administrative Information
|
IV.3.1)
|
Reference number attributed to the notice by the contracting authority
|
IV.3.2)
|
Previous publication(s) concerning the same contract
|
 |
|
 |
Other previous publications
|
IV.3.3)
|
Conditions for obtaining specifications and additional documents 29-04-2015
12:00
|
IV.3.4)
|
Time-limit for receipt of tenders or requests to participate 29-04-2015
12:00 |
IV.3.5)
|
Date of dispatch of invitations to tender or to participate to selected candidates 06-05-2015
|
IV.3.6)
|
Language or languages in which tenders or requests to participate can be drawn up
|
IV.3.7)
|
Minimum time frame during which the tenderer must maintain the tender
|
IV.3.8)
|
Conditions for opening tenders
|
|
|
|
|
Section VI: Other Information
|
VI.1)
|
Indicate whether this procurement is a recurrent one and the Estimated timing for further notices to be published
|
VI.2)
|
Does the contract relate to a Project/Programme financed by Community Funds? No
|
VI.3)
|
Additional Information
The dates given in Sections IV 3.4 and IV 3.5 are indicative only, and the Contracting Authority reserves the right to vary those dates if necessary.
Participants will be required to complete a PQQ which can be obtained via the Procurement Consultant at Beaumont School (see I.1).
The Contracting Authority reserves the right not to award a contract and to bring this procurement to an end at any point subject in particular to the results of its planning application.
For the avoidance of doubt, this contract is not divided into lots. The Contracting Authority is looking to make one appointment for the construction project and will not enter into multiple sub-contracts.
|
VI.4)
|
Procedures for appeal
|
VI.4.1)
|
Body responsible for appeal procedures
The Governing Body |
Oakwood Drive |
St Albans |
AL4 0XB |
UK |
simone.kilka-green@beaumont.herts.sch.uk |
|
|
|
|
|
|
Body responsible for mediation procedures
|
|
|
|
|
|
|
|
|
|
VI.4.2)
|
Lodging of appeals
Beaumont School will incorporate a maximum of 10 calendar day stand-still period at the point information on the award of the contract is communicated to tenderers at final contract award stage. This period allows unsuccessful tenderers to seek further debriefing from the contracting authority before the contract is entered into.
|
VI.4.3)
|
Service from which information about the lodging of appeals may be obtained
|
|
|
|
|
|
|
|
|
|
VI.5)
|
Dispatch date of this Notice 30-03-2015 |