Equipping Consultancy Service for Phase 2b of Great Ormond Street Hospital NHS Foundation Trust.

  • First published: 18 April 2015
  • Last modified: 18 April 2015
  • Version: N/A
  • This file may not be fully accessible.

  •  

Information icon

The buyer is not using this website to administer the notice.

To record your interest or obtain additional information or documents please find instructions within the Full Notice Text. (NOTE: Contract Award Notices and Prior Information Notices do not normally require a response)

Information icon
You are viewing an expired notice.

Contents

Summary

OCID:
Published by:
Great Ormond Street Hospital for Children NHS Trust
Authority ID:
AA23343
Publication date:
18 April 2015
Deadline date:
26 May 2015
Notice type:
Contract Notice
Has documents:
No
Has SPD:
No
Has Carbon Reduction Plan:
N/A

Abstract

Great Ormond Street Hospital for children NHS Foundation Trust is looking to appoint an Equipping Consultancy firm for the Phase 2B of the Redevelopment Programme, the Premier Inn Clinical Building due for completion July 2017. The 116-bed building includes a new surgery centre with two integrated operating theatres, a respiratory ward and an isolation unit for children with dermatology and rheumatology conditions or infectious diseases.

It is anticipated that these much-needed facilities will enable the hospital to treat up to 20 per cent more children with the most complex, rare and often life-threatening conditions. They will also allow parents or carers to stay by the child's bedside overnight, provide more room for children to play and eat together and areas for parents to have a break.

The construction timescale is expected to be as follows:

March 2015.

Date of completion of deconstruction of top floors:

September 2015.

Completion of construction of PICB frame and south extension:

November 2016.

Completion of fit out of each of the floors:

March 2017.

Construction handover:

April - July 2017.

Period of commissioning for PICB:

July 2017.

Date when patients are expected to commence moves into the PICB.

Full notice text

CONTRACT NOTICE – OFFICIAL JOURNAL

Section I: Contracting Authority

I.1)

Name, Address and Contact Point(s)


Great Ormond Street Hospital for Children NHS Foundation Trust

Level 2, Old Building, Chief Executive Offices

London

WC1N 3JH

UK

Great Ormond Street Hospital for Children NHS Foundation Trust

Valerio Roncaioli

+44 2078297927

valerio.roncaioli@gosh.nhs.uk

+44 2078298641

http://www.gosh.nhs.uk/


Checked box
Unchecked box
Checked box
Unchecked box
Checked box
Unchecked box

I.2)

Type of contracting Authority and Main Activity or Activities

Unchecked box
Unchecked box
Unchecked box
Unchecked box
Checked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Checked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
No

Section II: Object of the Contract

II.1)

Description

II.1.1)

Title attributed to the contract by the contracting authority

Equipping Consultancy Service for Phase 2b of Great Ormond Street Hospital NHS Foundation Trust.

II.1.2(a))

Type of works contract

II.1.2(b))

Type of supplies contract

II.1.2(c))

Type of service contract

II.1.2)

Main site or location of works, place of delivery or performance

Great Ormond Street Hospital NHS FoundationTrust, Great Ormond Street, London, WC1N 3JH.



UKI1

II.1.3)

This notice involves

Checked box
Unchecked box
Unchecked box

II.1.4)

Information on framework agreement (if applicable)

Unchecked box
Unchecked box

Number of participants to the framework agreement envisaged

Duration of the framework agreement

Justification for a framework agreement the duration of which exceeds four years

Estimated total value of purchases for the entire duration of the framework agreement

Frequency and value of the contracts to be awarded

II.1.5)

Short description of the contract or purchase(s)

Great Ormond Street Hospital for children NHS Foundation Trust is looking to appoint an Equipping Consultancy firm for the Phase 2B of the Redevelopment Programme, the Premier Inn Clinical Building due for completion July 2017. The 116-bed building includes a new surgery centre with two integrated operating theatres, a respiratory ward and an isolation unit for children with dermatology and rheumatology conditions or infectious diseases.

It is anticipated that these much-needed facilities will enable the hospital to treat up to 20 per cent more children with the most complex, rare and often life-threatening conditions. They will also allow parents or carers to stay by the child's bedside overnight, provide more room for children to play and eat together and areas for parents to have a break.

The construction timescale is expected to be as follows:

March 2015.

Date of completion of deconstruction of top floors:

September 2015.

Completion of construction of PICB frame and south extension:

November 2016.

Completion of fit out of each of the floors:

March 2017.

Construction handover:

April - July 2017.

Period of commissioning for PICB:

July 2017.

Date when patients are expected to commence moves into the PICB.

II.1.6)

Common Procurement Vocabulary (CPV)

79418000

II.1.7)

Contract covered by the Government Procurement Agreement (GPA)

Checked box

II.1.8)

Division into lots

No

II.1.9)

Will variants be accepted

No

II.2)

Quantity or Scope of the Contract

II.2.1)

Total quantity or scope

II.2.2)

Options

The Authority reserves the right to use this option to extend the contract for the appointed Phase 2b Equipping Consultancy Services tenderer for the Centre for Research into Rare Disease in Children (Phase 3a).

The new Centre for Research into Rare Disease in Children at Great Ormond Street Hospital (GOSH Phase 3a) on Guildford Street comprises circa 13 000 m² of accommodation over eight storeys with 2 levels of basement. This will be a state-of the-art research and medical building that will also include a dedicated outpatient facility.

The construction timescale is estimated to be as follows:

— Demolition Works — Commence 2nd quarter 2015;

— Main Building Works — Commence on site January 2016 — Completed February 2018;

— Period of commissioning — March - June 2018;

— Date when patients are expected to commence moves into the CRRDC — Summer 2018.

Provisional timetable for recourse to these options

Number of possible renewals

In the case of renewable supplies or service contracts, estimated time frame for subsequent contracts

II.3)

Duration of the contract or limit for completion

 18-08-2015 30-06-2017

Section III: Legal, Economic, Financial and Technical Information

III.1)

Conditions Relating to the Contract

III.1.1)

Deposits and guarantees required

Participants will be advised if this is necessary during the procurement. Parent company and/or other guarantees of performance and financial liability may be required if considered appropriate.

III.1.2)

Main Terms of financing and payment and/or reference to the relevant provisions

NHS terms and Conditions of Services will apply.

III.1.3)

Legal form to be taken by the grouping of suppliers, contractors or service providers to whom the contract is to be awarded

Bids from groupings of economic operators (consortia) will be accepted. In the event of a successful consortium bid, the Contracting Authority reserves the right to require groupings of entities to take a particular legal form and/or require that a single consortium member takes primary liability or that each member undertakes joint and several liability irrespective of the legal form adopted.

III.1.4)

Other particular conditions to which the performance of the contract is subject

III.2)

Conditions for Participation

III.2.1)

Personal situation of economic operators, including requirements relating to enrolment on professional or trade registers


As per the Pre-qualification Questionnaire.

III.2.2)

Economic and financial capacity


As per the Pre-qualification Questionnaire.




III.2.3)

Technical capacity


As per the Pre-qualification Questionnaire.




III.2.4)

Reserved contracts

Unchecked box
Unchecked box

III.3)

Conditions Specific to Service Contracts

III.3.1)

Is provision of the service reserved to a specific profession?

No

III.3.2)

Will legal entities be required to state the names and professional qualifications of the personnel responsible for the execution of the service?

Section IV: Procedure

IV.1)

Type of Procedure


Unchecked box Checked box
Unchecked box Unchecked box
Unchecked box Unchecked box

Justification for the choice of accelerated procedure

IV.1.1)

Have candidates already been selected?

No

IV.1.2)

Limitations on the number of operators who will be invited to tender or to participate

5

Objective criteria for choosing the limited number of candidates

As per the Pre-qualification Questionnaire.

IV.1.3)

Reduction of the number of operators during the negotiation or dialogue

Unchecked box

IV.2)

Award Criteria

No


Yes

No

IV.2.2)

An electronic auction will be used

No

IV.3 Administrative Information

IV.3.1)

Reference number attributed to the notice by the contracting authority

IV.3.2)

Previous publication(s) concerning the same contract

Unchecked box
Unchecked box


Other previous publications

IV.3.3)

Conditions for obtaining specifications and additional documents



 


IV.3.4)

Time-limit for receipt of tenders or requests to participate

 26-05-2015  12:00

IV.3.5)

Date of dispatch of invitations to tender or to participate to selected candidates

 08-06-2015

IV.3.6)

Language or languages in which tenders or requests to participate can be drawn up

Checked box    

IV.3.7)

Minimum time frame during which the tenderer must maintain the tender 

IV.3.8)

Conditions for opening tenders





Section VI: Other Information

VI.1)

Indicate whether this procurement is a recurrent one and the Estimated timing for further notices to be published


VI.2)

Does the contract relate to a Project/Programme financed by Community Funds?

No



VI.3)

Additional Information

If any actual or potential Candidate requires further information or has any query in respect of the PQQ by email, they should address their requests for further information (‘RFI’) to Procurement Manager, as follows:

Valerio Roncaioli

Great Ormond Street Hospital for Children NHS Foundation Trust

London

WC1N 3JH

Tel: +44 2078297927

Fax: +44 2078298641

Email: valerio.roncaioli@gosh.nhs.uk

And to the Interim Head of Commissioning and Space Management:

Bryony Freeman

Great Ormond Street Hospital for Children NHS Foundation Trust

London

Tel: +44 2078297810

Fax: +44 2078298641

Email: bryony.freeman@gosh.nhs.uk

VI.4)

Procedures for appeal

VI.4.1)

Body responsible for appeal procedures










Body responsible for mediation procedures










VI.4.2)

Lodging of appeals

VI.4.3)

Service from which information about the lodging of appeals may be obtained










VI.5)

Dispatch date of this Notice

 14-04-2015

Coding

Commodity categories

ID Title Parent category
79418000 Procurement consultancy services Business and management consultancy services

Delivery locations

ID Description
100 UK - All

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

About the buyer

Main contact:
valerio.roncaioli@gosh.nhs.uk
Admin contact:
N/a
Technical contact:
N/a
Other contact:
N/a

Further information

Date Details
No further information has been uploaded.

0800 222 9004

Lines are open 8:30am to 5pm Monday to Friday.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.