Contract Award Notice

EC0788 Main Contractor Kings Buildings Infrastructure (Contract 1)

  • First published: 02 August 2018
  • Last modified: 02 August 2018
  • Version: N/A
  •  

  • This file may not be fully accessible.

  •  

Information icon

The buyer is not using this website to administer the notice.

To record your interest or obtain additional information or documents please find instructions within the Full Notice Text. (NOTE: Contract Award Notices and Prior Information Notices do not normally require a response)

Contents

Summary

OCID:
Published by:
University Of Edinburgh
Authority ID:
AA21242
Publication date:
02 August 2018
Deadline date:
-
Notice type:
Contract Award Notice
Has documents:
No
Has SPD:
No
Has Carbon Reduction Plan:
N/A

Abstract

Award Notice for this first contract focusses on the utilities infrastructure within the central zone of the Campus and the replacement of the switchgear in 4 sub-stations. It also includes HV and LV cable replacement and various LV panels complete with future generator connections to significantly reduce the risk of the power outages and supporting future resilience. The main elements of this first contract are:

— replacement of the out-dated High Voltage (HV) and Low Voltage (LV) switch-gear in sub-stations A, B, C and D,

— replacement of HV electric cable between sub-station A and B,

— extension of the King’s Buildings (KB) Energy Centre to accommodate an additional boiler and associated plant to provide additional site heating capacity,

— upgrade and diversion of district heating pipes, sewer lines, data/communication cables and gas and water pipework.

This first contract will have wide reaching disruption on the experience of Campus users day to day therefore it is essential that the impact is minimised as much as possible. The electrical works will affect every building on the Campus, power / heating shut downs will need to be coordinated with building users and logistical organisation of the works will need to be carefully managed.

Scope of Appointment:

A large proportion of the existing King’s Buildings campus infrastructure dates back to the time that the Joseph Black Building was opened in 1922 and over the period since then the campus has grown and evolved in an ad-hoc manner to serve in excess of 30 major buildings.

This initial contract focuses on attending to the legacy infrastructure in the area between Union Square (gate 2 access) and Colin MacLaurin Road (gate 3 access), upgrading the infrastructure whilst clearing the Nucleus site of underground utilities.

The main elements of this first contract are the replacement of:

— outdated switchgear in sub-stations A, B, C and D,

— High Voltage electric cable between sub-station A and B,

— to disconnect and remove existing feeder pillars serving various buildings,

— LV switchgear in various buildings as part of the enabling works,

— Scottish Power network cabling diversions and decommissioning,

— the Physical extension of the KB Energy Centre, to accommodate a proposed additional boiler and associated plant to provide additional site boiler capacity,

— upgrade and diversion of district heating pipes,

— sections of sewer lines have defects that are affecting performance, sections are under new build footprints and there is also a requirement to relieve pressure on the external sewer by diverting storm drainage to attenuation and diverting foul sewer to different outfalls,

— data / communication cables to be diverted to clear the Nucleus site,

— Gas — decommissioning and diversion to be diverted to clear the Nucleus site,

— water pipework — to be upgraded and diverted to clear the Nucleus site.

The investment priorities for infrastructure are informed by risk management, business continuity, long term sustainability and required essential resilience, summarised as the following:

Maintain safety, integrity and performance of the campus infrastructure whilst ensuring long-term sustainability and support the proposed Masterplan and business continuity. Planned interventions prior to potential asset failure, when asset performance and reliability fall below an acceptable operational limits and cannot be restored without an unacceptable business risks, financial risk and/or system risk exposure.

Reduce the risk of service interruptions associated with infrastructure failures, through interventions targeted on assets at or approaching of critical condition.

Target investment based on an assessment of impact and consequences of failure, customer sensitivity to supply disturbances, asset performance and environmental considerations.

Full notice text

Contract award notice

Results of the procurement procedure

Section I: Contracting entity

I.1) Name and addresses

University Of Edinburgh

Charles Stewart House, 9-16 Chambers Street

Edinburgh

EH1 1HT

UK

E-mail: elizabeth.lebost@ed.ac.uk

NUTS: UKM75

Internet address(es)

Main address: http://www.ed.ac.uk/schools-departments/procurement/supplying

Address of the buyer profile: http://www.publiccontractsscotland.gov.uk/search/Search_AuthProfile.aspx?ID=AA00107

I.2) Joint procurement

The contract is awarded by a central purchasing body

I.4) Type of the contracting authority

Body governed by public law

I.5) Main activity

Education

Section II: Object

II.1) Scope of the procurement

II.1.1) Title

EC0788 Main Contractor Kings Buildings Infrastructure (Contract 1)

Reference number: EC0788

II.1.2) Main CPV code

45214400

 

II.1.3) Type of contract

Works

II.1.4) Short description

AWARD Notice for the University of Edinburgh appointing a Design and Build Main Contractor on a single stage design and build contract form to deliver the first of 6 contracts of the KB Infrastructure project.

II.1.6) Information about lots

This contract is divided into lots: No

II.1.7) Total value of the procurement

Value excluding VAT: 6 427 694.63  GBP

II.2) Description

II.2.2) Additional CPV code(s)

45214400

II.2.3) Place of performance

NUTS code:

UKM75


Main site or place of performance:

Our Kings Building campus.

II.2.4) Description of the procurement

Award Notice for this first contract focusses on the utilities infrastructure within the central zone of the Campus and the replacement of the switchgear in 4 sub-stations. It also includes HV and LV cable replacement and various LV panels complete with future generator connections to significantly reduce the risk of the power outages and supporting future resilience. The main elements of this first contract are:

— replacement of the out-dated High Voltage (HV) and Low Voltage (LV) switch-gear in sub-stations A, B, C and D,

— replacement of HV electric cable between sub-station A and B,

— extension of the King’s Buildings (KB) Energy Centre to accommodate an additional boiler and associated plant to provide additional site heating capacity,

— upgrade and diversion of district heating pipes, sewer lines, data/communication cables and gas and water pipework.

This first contract will have wide reaching disruption on the experience of Campus users day to day therefore it is essential that the impact is minimised as much as possible. The electrical works will affect every building on the Campus, power / heating shut downs will need to be coordinated with building users and logistical organisation of the works will need to be carefully managed.

Scope of Appointment:

A large proportion of the existing King’s Buildings campus infrastructure dates back to the time that the Joseph Black Building was opened in 1922 and over the period since then the campus has grown and evolved in an ad-hoc manner to serve in excess of 30 major buildings.

This initial contract focuses on attending to the legacy infrastructure in the area between Union Square (gate 2 access) and Colin MacLaurin Road (gate 3 access), upgrading the infrastructure whilst clearing the Nucleus site of underground utilities.

The main elements of this first contract are the replacement of:

— outdated switchgear in sub-stations A, B, C and D,

— High Voltage electric cable between sub-station A and B,

— to disconnect and remove existing feeder pillars serving various buildings,

— LV switchgear in various buildings as part of the enabling works,

— Scottish Power network cabling diversions and decommissioning,

— the Physical extension of the KB Energy Centre, to accommodate a proposed additional boiler and associated plant to provide additional site boiler capacity,

— upgrade and diversion of district heating pipes,

— sections of sewer lines have defects that are affecting performance, sections are under new build footprints and there is also a requirement to relieve pressure on the external sewer by diverting storm drainage to attenuation and diverting foul sewer to different outfalls,

— data / communication cables to be diverted to clear the Nucleus site,

— Gas — decommissioning and diversion to be diverted to clear the Nucleus site,

— water pipework — to be upgraded and diverted to clear the Nucleus site.

The investment priorities for infrastructure are informed by risk management, business continuity, long term sustainability and required essential resilience, summarised as the following:

Maintain safety, integrity and performance of the campus infrastructure whilst ensuring long-term sustainability and support the proposed Masterplan and business continuity. Planned interventions prior to potential asset failure, when asset performance and reliability fall below an acceptable operational limits and cannot be restored without an unacceptable business risks, financial risk and/or system risk exposure.

Reduce the risk of service interruptions associated with infrastructure failures, through interventions targeted on assets at or approaching of critical condition.

Target investment based on an assessment of impact and consequences of failure, customer sensitivity to supply disturbances, asset performance and environmental considerations.

II.2.5) Award criteria

Quality criterion: Quality / Weighting: 40

Price / Weighting:  60

II.2.11) Information about options

Options: No

II.2.13) Information about European Union funds

The procurement is related to a project and/or programme financed by European Union funds: No

II.2.14) Additional information

Economic operators may be excluded from this competition if there are any of the situations referred to in Regulation 58 of the Public Contracts (Scotland) Regulations 2015.

Section IV: Procedure

IV.1) Description

IV.1.1) Type of procedure

Restricted procedure

IV.1.8) Information about Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: Yes

IV.2) Administrative information

IV.2.1) Previous publication concerning this procedure

Notice number in the OJ S:

2017/S 172-351661

Section V: Award of contract

Contract No: EC0788

A contract/lot is awarded: Yes

V.2 Award of contract

V.2.1) Date of conclusion of the contract

18/07/2018

V.2.2) Information about tenders

Number of tenders received: 2

The contract has been awarded to a group of economic operators: No

V.2.3) Name and address of the contractor

FES

Forth House, Pirnhall Business Park

Stirling

FK7 8HW

UK

NUTS: UK

The contractor is an SME: No

V.2.4) Information on value of the contract/lot (excluding VAT)

Total value of the contract/lot: : 6 427 694.63  GBP

V.2.5) Information about subcontracting

Section VI: Complementary information

VI.3) Additional information

(SC Ref:551941)

VI.4) Procedures for review

VI.4.1) Review body

University Of Edinburgh

Charles Stewart House, 9-16 Chambers Street

Edinburgh

EH1 1HT

UK

Telephone: +44 1316502508

Internet address(es)

URL: http://www.ed.ac.uk/schools-departments/procurement/supplying

VI.5) Date of dispatch of this notice

31/07/2018

Coding

Commodity categories

ID Title Parent category
45214400 Construction work for university buildings Construction work for buildings relating to education and research

Delivery locations

ID Description
100 UK - All

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

About the buyer

Main contact:
elizabeth.lebost@ed.ac.uk
Admin contact:
N/a
Technical contact:
N/a
Other contact:
N/a

Further information

Date Details
No further information has been uploaded.

0800 222 9004

Lines are open 8:30am to 5pm Monday to Friday.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.