Engagement process description
The Future Asylum Contracts Transformation Team will carry out the engagement in three phases, the first phase will focus on gathering market feedback between June and July 2025, and the second phase will focus on validating strategy with market insights between July and September 2025. The third phase will focus on the latest FACT strategy which has been updated to reflect Ministerial steer, government priorities and market developments and testing this with the market to ensure sufficient rigour and validate what may be proposed in the future ITTs. The objective is to identify potential risks early. Further phases may be included in advance of any formal procurement launch.
It is our intention to invite those suppliers that express an interest in this opportunity. In the event of high demand, we reserve the right to limit attendance to ensure fair and manageable engagement. Where attendance is limited, efforts will be made to ensure a representative cross-section of the market is included. For example, 13 suppliers were invited to 1-2-1 meetings between 29th August – 5th September 2025. When choosing which suppliers to speak with, the following four areas were considered:
- RFI 2 responses: Supplier responses to every RFI 2 question were reviewed to identify any feedback that highlighted innovative approaches, especially if relevant to one of the areas the Home Office wanted to test during the 1-2-1 sessions, namely the delivery model, route to market and lotting strategy.
- Service area coverage: The Home Office wanted to ensure a fair representation of different suppliers covering the difference service areas in the FACT procurement.
- National and regional coverage: The Home Office aimed for mix of national and regional suppliers to provide give a balanced view in the subject areas tested in the supplier 1-2-1s.
- Mix of supplier size: The Home Office wanted feedback from suppliers of all sizes to ensure the views of both the biggest players in the market and SMEs were covered for each service area.
Suppliers who are unable to attend will not be disadvantaged in any future procurement and will be provided with access to any relevant materials or outputs from the engagement session.
For the purposes of this Preliminary Market Engagement Notice, the estimated contract value has been listed as £0. This figure does not reflect the expected final value of the contract. The actual estimated value is currently being finalised and will be shared as part of the ongoing market engagement process.
1. To express an interest, participants must first be registered on the Home Office eSourcing Suite. If you have not yet registered, this can be done online at https://homeoffice.app.jaggaer.com/web/login.html by following the link. Please note that, to register, you must have a valid DUNS number (as provided by Dun and Bradstreet) for the organisation which you are registering and who will be entering into a contract if invited to do so.
2. Send an 'Expression of Interest' email following the instructions:
Email to: asapprocurement@homeoffice.gov.uk
Email title: Expression of Interest - ASAP - NDA Request - (DUNS number)
3. The email must include the following:
Supplier name (as on Companies House)
DUNS number
Jaggaer registration details
Contact person - Name, job title, email address, contact number
4. The suppliers will be added to the NDA event on Jaggaer to access the NDA. This will contain the instruction to access and return signed copies.
5. The suppliers will receive countersigned NDAs and access to the Background Note providing details of the services in scope, engagement process and timelines.
PHASE 1: Gathering Market Feedback
ASAP Industry Day (In-person, London):
Publish Preliminary Market Engagement Notice – 28 May 2025
(Updated on August 27 )
Industry Day – 10 June 2025
Request for Information (RFI – Round 1):
RFI live –16 June 2025
RFI response deadline; 16:00 BST on – 04 July 2025
PHASE 2: Validating Strategy with Market Insights
Request for Information (RFI – Round 2):
RFI live – 22 July 2025
RFI response deadline – 8 August 2025
Supplier 1:1s:
Notification of supplier 1:1s – 27 August 2025
Hold virtual supplier 1:1s – 29 August 2025 to 5 September 2025
Request for Information (RFI – Round 3):
RFI live – 8 September 2025
RFI response deadline; 16 BST on – 26 September 2025
PHASE 3: Testing Strategy pre-ITT
Request for Information (RFI - Round 4)
RFI live - 25 November 2025
RFI response deadline - 19 December 2025
Request for Information (RFI - Round 4.5):
RFI live - 15 December 2025
RFI response deadline - 16 January 2026
Request for Information (RFI - Round 5):
RFI live – 20 April 2026
RFI response deadline – 1 May 2026
FACT Industry Day - Pre-ITT Launch to provide context of all the key commercial changes pre-ITT launch from the initial industry day and summarise the key market engagement findings the Home Office has collected to-date.
Industry Day – Week Commencing 13th April 2026
The Home Office intends to host an Industry Day during the week commencing 13th April 2026. The final date and location will be confirmed in invitations issued via Jaggaer once arrangements have been finalised.
If a supplier is interested in attending and has not previously expressed an interest in this procurement, please follow the steps set out in this notice to register your interest.
Supplier Update Session
The Home Office intends to host an online Supplier Update Session anticipated for mid-September. The final date and details will be confirmed in invitations issued via Jaggaer once arrangements have been finalised.
The event is expected to include:
• An overview of the requirements and programme objectives.
• The finalised procurement approach.
• Opportunities for suppliers to ask clarification questions.
If a supplier is interested in attending and has not previously expressed an interest in this procurement, please follow the steps set out in this notice to register your interest
Please Note:
The dates above are indicative and are subject to change.
This is an open process, and the Home Office welcomes any new suppliers that have joined at a later stage. The Home Office will ensure suppliers have full visibility of all activity to-date.
The Home Office reserves the right to amend the Market Engagement process at a later date if needed. Any changes will be updated on the Preliminary Market Engagement Notice and through Jaggaer.