II.2.3) Place of performance
NUTS code:
UKM6
Main site or place of performance:
Stornoway, Eilean Siar.
II.2.4) Description of the procurement
Procurement of contractor for a new deep water port within Stornoway Harbour. The anticipated contract works include the following:
1) dredging between 500 000 m3 and 700 000 m3 of the seabed to increase water depths to 10 m below Chart Datum at the berths and in adjoining manoeuvring areas;
2) re-use of dredge arisings to form a new platform and laydown area; removal of material unsuitable for re-use to the nearby Arnish disposal site;
3) rock blasting and associated earthworks to create infill to supplement dredge material and to clear space for the access and link roads;
4) two quay walls, one to provide part of the main berth approximately 191 m long and one of approximately 140 m to provide a berth for ferries and other ro-ro vessels;
5) an open piled finger pier approximately 119 m long to the south of and extending the main berth to approximately 310 m in length;
6) a linkspan and linkspan dolphins at the freight ferry berth;
7) a heavy lift area on the quayside to allow transfer of heavy components to and from vessels;
8) a heavy duty pontoon, 100 m long and 4 m wide, to be located at the west side of the finger pier, with an access bridge from the finger pier;
9) fendering to all berthing faces;
10) quay furniture and aids to navigation;
11) utility services (electricity, water, telecoms), external lighting, tanks for storage of marine fuel and potable water and a new substation;
12) CCTV and other safety/security measures such as fences and barriers;
13) packaged sewage treatment plant and outfalls for surface water drainage;
14) services infrastructure within the laydown area;
15) a new access road approximately 375 m long to connect the port to the existing Arnish Road;
16) a 25 m wide access link road approximately 650 m long between the new berth and Arnish Point Industrial Estate to allow the transfer of large components such as offshore modules and large windfarm components;
17) removal of elements of the wreck of the SS Alabama which are above 8 m below Chart Datum (removed elements to be placed within the footprint of the wreck).
See Instructions to bidders for further information.
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 22
This contract is subject to renewal: No
II.2.9) Information about the limits on the number of candidates to be invited
Envisaged number of candidates: 5
Objective criteria for choosing the limited number of candidates:
Economic and financial standing:
— turnover,
— net profit margin,
— provision of three years of finalised accounts,
— professional Indemnity insurance cover of GBP 10 million,
— employer's liability insurance cover of GBP 10 million,
— contractor's all risks insurance cover of GBP 40 million,
— public liability insurance cover of GBP 10 million.
Technical and professional ability:
— Relevant examples of works carried out in the past 10 years. A completed reference from the client using the template provided confirming that the bidder’s performance has been satisfactory must be submitted for each project. In the event that a bidder is not able to provide this for reasons outside their control, a bidder should obtain a reference from an alternative source, e.g. client’s engineer or other independent party involved in the project.
— Technicians or technical bodies to carry out the works.
— Supply chain management and/or tracking systems used.
— Environmental management measures which the bidder will be able to use when performing the contract.
— Managerial staff for the last 3 years.
— Quality assurances schemes/procedures, including evidence of competence to act as a Principal contractor.
— Environmental management system/procedures.
Details of the information required and minimum requirements are set out in the instructions to bidders document.
II.2.10) Information about variants
Variants will be accepted:
Yes
II.2.11) Information about options
Options:
Yes
Description of options:
Any requirements for optional items will be set out in the Invitation to Tender.
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No