CONTRACT NOTICE – OFFICIAL JOURNAL
|
Section I: Contracting Authority
|
I.1)
|
Name, Address and Contact Point(s)
|
|
Devon and Somerset Fire and Rescue Authority723645339 |
Service Headquarters, The Knowle, Clyst St George |
Exeter |
EX3 0NW |
UK |
Bridget Phillips |
+44 1392872200 |
procurement@dsfire.gov.uk |
|
http://www.dsfire.gov.uk
https://uk.eu-supply.com/ctm/Supplier/CompanyInformation/Index/30504
https://uk.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=12948&B=BLUELIGHT
https://uk.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=12948&B=BLUELIGHT
|
|
|
|

 |
|

 |
|

 |
|
I.2)
|
Type of contracting Authority and Main Activity or Activities
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
|
|
No |
Section II: Object of the Contract
|
II.1)
|
Description
|
II.1.1)
|
Title attributed to the contract by the contracting authorityDS144-15 Supply and Retrofit of Auxiliary Batteries. |
II.1.2(a))
|
Type of works contract
|
II.1.2(b))
|
Type of supplies contract
|
II.1.2(c))
|
Type of service contract27 |
II.1.2)
|
Main site or location of works, place of delivery or performance
UKK |
II.1.3)
|
This notice involves
|
 |
|
 |
|
 |
|
II.1.4)
|
Information on framework agreement (if applicable)
|
 |
|
 |
|
|
Number of participants to the framework agreement envisaged
|
|
Duration of the framework agreement
|
|
Justification for a framework agreement the duration of which exceeds four years
|
|
Estimated total value of purchases for the entire duration of the framework agreement
|
|
Frequency and value of the contracts to be awarded |
II.1.5)
|
Short description of the contract or purchase(s)
The Authority is seeking to appoint a Contractor to supply and retrofit auxiliary batteries to a number of their operational vehicles. The auxiliary batteries are required to support the communication equipment.
Potential Providers are able to bid for this requirement based on the following options:
— Option 1 — The auxiliary battery retrofits are carried out at the Contractors Premises (requiring the Contractor to collect and deliver the Vehicles and have their own (or access to) suitable Premises to carry out the Service).
— Option 2 — The auxiliary battery retrofits are carried out at the Authority’s Premises.
Potential Providers are able to submit a tender based on being able to deliver both of these options or 1 option only. The Authority will decide which option to award, once the tender evaluation stage is complete — It will be at the Authority’s discretion as to which option is awarded.
The contract will be awarded to a single Contractor and will only be open and available for the use of Devon and Somerset Fire and Rescue Service. The relatively low value of the Contract and cap of 4 vehicles that the Authority can release at any 1 time is considered achievable for all organisation sizes (including Small and Medium Enterprises).
The contract is anticipated to commence in June 2016.
Procurement documentation can be found on the Authority‘s e-tendering portal located at https://uk.eu-supply.com/login.asp?B=BLUELIGHT
|
II.1.6)
|
Common Procurement Vocabulary (CPV)
|
|
|
|
50117000 |
|
|
|
|
|
II.1.7)
|
Contract covered by the Government Procurement Agreement (GPA) |
II.1.8)
|
Division into lots No |
II.1.9)
|
Will variants be accepted
No |
II.2)
|
Quantity or Scope of the Contract
|
II.2.1)
|
Total quantity or scopeThe contract will be for the supply and retrofit of auxiliary batteries to Medium Rescue Pumping Appliances (MRP‘s) and may include a second optional phase of retrofits to Special Vehicles (Prime Movers, Rescue Tenders, Water Carriers, Operational Support vehicles etc.,).
DSFRS currently has 110 MRP’s and 48 Special Vehicles within its fleet of vehicles (including national resilience vehicles). DSFRS does not intend to retrofit auxiliary batteries to all MRP‘s, only those with a remaining operational life that justifies the investment. Although not confirmed, it is likely that a minimum of 40 MRP’s will require retrofitting. At this early stage, it is not known how many Special Vehicles would be retrofitted if DSFRS proceeded with the second optional phase.
To maintain operational resilience, the Authority will only release 4 vehicles for retrofit at any 1 time. |
|
90 000400 000 GBP |
II.2.2)
|
OptionsOptional second phase — A second optional phase to supply and retrofit auxiliary batteries to Special Vehicles has been included within the scope of this contract. At this stage, no funding has been identified for this phase and it is not known how many Special Vehicles would be retrofitted if DSFRS proceeded with it.
Option to extend the contract — The Authority proposes to enter into the contract for a period of 2 years with the Contractor. The Authority may extend the contract for a further period or periods not exceeding a total contract period of 4 years. |
|
Provisional timetable for recourse to these options
|
|
Number of possible renewals
|
|
In the case of renewable supplies or service contracts, estimated time frame for subsequent contracts
|
II.3)
|
Duration of the contract or limit for completion024 |
Section III: Legal, Economic, Financial and Technical Information
|
III.1)
|
Conditions Relating to the Contract
|
III.1.1)
|
Deposits and guarantees required
Minimum insurance levels:
Employers (Compulsory) Liability — 5 000 000 GBP (five million pounds);
Public Liability* — 5 000 000 GBP (five million pounds);
Products Liability* — 5 000 000 GBP (five million pounds).
*Public Liability/Products Liability shall include cover for the following:
1) Property/Vehicles being worked upon;
2) Hot work (if applicable).
And should include cover for the following:
3) Advice, design and specification liability provided as part of a package for supply and installation of products;
4) Financial loss;
5) Failure to perform (efficacy).
Potential providers who do not have in place (or cannot commit to obtain prior to the commencement of the contract) the desirable cover within their Public Liability/Products Liability insurance (those listed as 3), 4) and 5) above), shall have separate Professional Indemnity insurance. In this instance the level of Professional Indemnity insurance required is a limit of indemnity of not less than 1 000 000 GBP (one million pounds) for each individual claim or 5 000 000 GBP (five million pounds) in aggregate.
|
III.1.2)
|
Main Terms of financing and payment and/or reference to the relevant provisions
Determined within the tender documentation.
|
III.1.3)
|
Legal form to be taken by the grouping of suppliers, contractors or service providers to whom the contract is to be awarded
Organisations wishing to bid as either a consortium or subcontracting arrangement do not require a specific legal form in order to submit a tender. If the potential provider is a consortium, each member of the consortium will be jointly and severally liable for performance of the contract or shall select from amongst themselves a lead partner for the purposes of the procurement. All correspondence in relation to this procurement will be sent to the Lead Partner only.
|
III.1.4)
|
Other particular conditions to which the performance of the contract is subject
|
III.2)
|
Conditions for Participation
|
III.2.1)
|
Personal situation of economic operators, including requirements relating to enrolment on professional or trade registers
Economic operators must be registered with the appropriate trade or professional register(s) in the EU member state where it is established (as set out in Annex XI of directive 2014/24/EU of the European Parliament and of the Council) under the conditions laid down by that member state.
|
III.2.2)
|
Economic and financial capacity
Potential Providers will be assessed in accordance with Section 5 of Chapter 2 of the Public Contracts Regulations 2015 on the basis of information provided in response to the Invitation to Tender. Completed responses to the Invitation to Tender must be returned via the e-tendering portal before the deadline for receipt of responses as notified in Section IV.3.4) of this OJEU Notice.
The Authority will review a range of economic information to evaluate your organisation‘s economic and financial standing. In addition to the requested financial information in the Invitation to Tender, the Authority may consult Experian reports and other credit rating or equivalent reports depending on where your organisation is located. In particular, the Authority will consider financial strength and risk of business failure.
If your organisation is evaluated as high risk the Authority may:
— Ask for additional information, including information relating to your parent company, if applicable; and/or
— Require a parent company guarantee or a performance bond.
|
III.2.3)
|
Technical capacity
Refer to ITT documentation — https://uk.eu-supply.com/login.asp?B=BLUELIGHT
Refer to ITT documentation — https://uk.eu-supply.com/login.asp?B=BLUELIGHT
|
III.2.4)
|
Reserved contracts
|
 |
|
 |
|
III.3)
|
Conditions Specific to Service Contracts
|
III.3.1)
|
Is provision of the service reserved to a specific profession? No |
III.3.2)
|
Will legal entities be required to state the names and professional qualifications of the personnel responsible for the execution of the service? No |
Section IV: Procedure
|
IV.1)
|
Type of Procedure
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
Justification for the choice of accelerated procedure
|
IV.1.1)
|
Have candidates already been selected? No |
IV.1.2)
|
Limitations on the number of operators who will be invited to tender or to participate |
|
|
Objective criteria for choosing the limited number of candidates
|
IV.1.3)
|
Reduction of the number of operators during the negotiation or dialogue
|
 |
|
IV.2)
|
Award Criteria
|
|
No
|
|
|
|
Yes
|
|
No
|
IV.2.2)
|
An electronic auction will be used No
|
IV.3 Administrative Information
|
IV.3.1)
|
Reference number attributed to the notice by the contracting authority
DS144-15
|
IV.3.2)
|
Previous publication(s) concerning the same contract
|
 |
|
 |
2015/S 127-232902 04-07-2015
Other previous publications2015/S 154-284263 12-08-2015 |
IV.3.3)
|
Conditions for obtaining specifications and additional documents 11-03-2016
13:30
|
IV.3.4)
|
Time-limit for receipt of tenders or requests to participate 11-03-2016
14:00 |
IV.3.5)
|
Date of dispatch of invitations to tender or to participate to selected candidates
|
IV.3.6)
|
Language or languages in which tenders or requests to participate can be drawn up
|
IV.3.7)
|
Minimum time frame during which the tenderer must maintain the tender 006
|
IV.3.8)
|
Conditions for opening tenders
|
|
Tenders will be opened by Devon and Somerset Fire and Rescue Service employees, located at DSFRS Headquarters, The Knowle, Clyst St George, Exeter, Devon, EX3 0NW.
|
|
11-03-2016
14:00
|
Section VI: Other Information
|
VI.1)
|
Indicate whether this procurement is a recurrent one and the Estimated timing for further notices to be published
|
VI.2)
|
Does the contract relate to a Project/Programme financed by Community Funds? No
|
VI.3)
|
Additional Information
The deadline for Potential Providers to confirm attendance at the on-site vehicle surveys is on or before Tuesday 23.2.2016 via the messaging area within the e-tendering portal — https://uk.eu-supply.com/login.asp?B=BLUELIGHT
The date for the on-site vehicle surveys is Wednesday 2.3.2016, at:
Devon and Somerset Fire and Rescue Service, Knights Road, Chelston Business Park, Wellington, Somerset, TA21 9JH.
See tender documentation (Part A — ITT Supporting Information, section 1.6) for further information on vehicle surveys.
|
VI.4)
|
Procedures for appeal
|
VI.4.1)
|
Body responsible for appeal procedures
|
|
|
|
|
|
|
|
|
|
|
|
Body responsible for mediation procedures
|
|
|
|
|
|
|
|
|
|
VI.4.2)
|
Lodging of appeals
|
VI.4.3)
|
Service from which information about the lodging of appeals may be obtained
|
|
|
|
|
|
|
|
|
|
VI.5)
|
Dispatch date of this Notice 29-01-2016 |