Description of the goods or services required
Overview:
As part of the Transport for Wales’ (TfW) Core Valley Lines (CVL) Project, Balfour Beatty Rail have been asked to submit a quotation for the project’s Test and Commissioning requirements.
Balfour Beatty Rail is seeking to engage the market for proposals which shall include the Factory Acceptance testing (FAT) in Glasgow and Site Acceptance Testing (SAT) in Wales at 7 Traction Power compounds.
1. Taff’s Well MPTSS:
Integrated FAT testing at Huntly Road Glasgow premises of the following equipment
>Taffs Well MPTSS - SCADA Equipment x1 N/A
>Taffs Well MPTSS - HV Switchgear (panels) x2 Yes
>Taffs Well MPTSS - LV C/O Panel x1 Yes
>Taffs Well MPTSS - RCBB CT's x2 Yes
>Taffs Well MPTSS - Battery Charger x1 Yes
>Taffs Well MPTSS - HV Cables x2 N/A
Testing to include the following:
25kV Switchgear:
>General inspection
>Uploading of protection configuration and protection files to Micom P44T and P143 relays
>CT Tests (secondary resistance, Polarity)
>CT Tests, Differential Schemes (primary injection)
>Functional Tests, including relay secondary injection with Omicron relay test set, to test settings provided by BBR
>Simulation of all controls and indications during SCADA integrated testing
LV C/O Panel:
>General inspection
>Contact Resistance
>Plant Resistance and Voltage Withstand Tests
>Under Voltage relay test
>Function test
RCCB CT’s:
>Flick Test (Polarity)
>Secondary resistance
>Insulation Resistance
>Excitation (mag curves)
>Ratio
Battery Charger:
>General inspection
>Battery Chargers (Functionality and Discharge)
Integrated SAT testing at Wales:
Testing to include the following:
>Taffs Well MPTSS - SCADA Equipment x1 N/A
>Taffs Well MPTSS - HV Switchgear (panels) x2 Yes
>Taffs Well MPTSS - LV C/O Panel x1 Yes
>Taffs Well MPTSS - RCBB CT's x2 Yes
>Taffs Well MPTSS - Battery Charger x1 Yes
>Taffs Well MPTSS - HV Cables x2 Yes
25kV Switchgear:
>Uploading of final protection configuration and protection files to Micom P44T and P143 relays.
>Secondary inject relays with Omicron relay test set to final settings provided by BBR
>CT Tests (secondary resistance)
>Busbar contact resistance testing (200amp Ductor)
>Simulation of all controls and indications during SCADA integrated testing
LV C/O Panel:
>Contact Resistance (once incoming cables connected)
>Function test to SCADA
RCCB CT’s:
>Secondary resistance
Battery Charger:
>Function test to SCADA
HV Cables:
>Drum test 5kV Megger 1 minute
>Serving Test after installation 10kV DC 1minute
>Pressure test 75kV DC
DNO Cabinet:
>General inspection
>Contact Resistance
>Plant Resistance and Voltage Withstand Tests
>Under Voltage relay test
>Function test
>Earth Fault Loop Impedance
>Fault Current Testing
Isolating Transformer:
>General inspection
>Contact Resistance
>Plant Resistance and Voltage Withstand Tests
>Under Voltage relay test
>Function test
Commissioning into service:
>Contractor to provide commissioning resource and Level A for the following
>Soak test
>Downloading of protection relays data after S/C
2. Tonteg Feeder Station (FS):
Same tests as specified for Taffs Well: FAT & SAT
>Tonteg FS SCADA Equipment - x1 N/A FAT & SAT
>Tonteg FS HV Switchgear (panels) - x8 Yes FAT & SAT
>Tonteg FS LV C/O Panel - x1 Yes FAT & SAT
>Tonteg FS RCBB CT's - x2 Yes FAT & SAT
>Tonteg FS Battery Charger - x1 Yes FAT & SAT
>Tonteg FS HV Cables - x8 N/A FAT / Yes SAT
3. Radyr MPTSS:
Same tests as specified for Taffs Well FAT and SAT
>Radyr MPTSS SCADA Equipment - x1 N/A FAT & SAT
>Radyr MPTSS HV Switchgear (panels) - x11 Yes FAT & SAT
>Radyr MPTSS LV C/O Panel - x1 Yes FAT & SAT
>Radyr MPTSS RCBB CT's - x1 Yes FAT & SAT
>Radyr MPTSS Battery Charger - x1 Yes FAT & SAT
>Radyr MPTSS HV Cables - x11 N/A FAT & SAT
4. Queen St North MPTSS:
Same tests as specified for Taffs Well FAT and SAT
>Queen St MPTSS SCADA Equipment - x1 N/A FAT & SAT
>Queen St MPTSS HV Switchgear (panels) - x8 Yes FAT & SAT
>Queen St MPTSS LV C/O Panel - x1 Yes FAT & SAT
>Queen St MPTSS RCBB CT's - x1 Yes FAT & SAT
>Queen St MPTSS Battery Charger - x1 Yes FAT & SAT
>Queen St MPTSS HV Cables - x8 N/A FAT & SAT
5. Pontypridd TSS:
Same tests as specified for Taffs Well FAT and SAT
>Pontypridd TSS SCADA Equipment - x1 N/A FAT & SAT
>Pontypridd TSS HV Switchgear (panels) - x5
>Pontypridd TSS LV C/O Panel - x1 Yes FAT & SAT
>Pontypridd TSS RCBB CT's - x1 Yes FAT & SAT
>Pontypridd TSS Battery Charger - x1 Yes FAT & SAT
>Pontypridd TSS HV Cables - x5 N/A FAT & SAT
6. Ninian Park FS:
Same tests as specified for Taffs Well FAT and SAT
>Ninian Park FS SCADA Equipment - x1 N/A FAT & SAT
>Ninian Park FS HV Switchgear (panels) - x9 Yes FAT & SAT
>Ninian Park FS LV C/O Panel - x1 Yes FAT & SAT
>Ninian Park FS RCBB CT's - x1 Yes FAT & SAT
>Ninian Park FS Battery Charger - x1 Yes FAT & SAT
>Ninian Park FS HV Cables - x9 N/A FAT & SAT
7. Abercynon TSS:
Same tests as specified for Taffs Well FAT and SAT
>Abercynon TSS SCADA Equipment - x1 N/A FAT & SAT
>Abercynon TSS HV Switchgear (panels) - x4 Yes FAT & SAT
>Abercynon TSS LV C/O Panel - x1 Yes FAT & SAT
>Abercynon TSS RCBB CT's - x1 Yes FAT & SAT
>Abercynon TSS Battery Charger - x1 Yes FAT & SAT
>Abercynon TSS HV Cables -x4 N/A FAT & SAT
a)The assumption to be that all Test plans and procedures to be produced by BBR at this stage.
b)All costs should be inclusive of Travel, Training, Parking, PPE etc, BBR will provide site
safety and welfare, BBR will produce all the relevant T&C documentation which each
contractor would be expected to complete in order to achieve the tests listed in the
attached document.
c)Final hand back documentation must be completed and returned in an acceptable manner
within four weeks (20 working days) of each commissioning stage.
Programme:
Subcontract Start Date:
>FAT Start: June 2021
>SAT Start: Nov 2021
Subcontract Completion Date:
>FAT: Dec 2021
>SAT: Oct 2022
Tender Documents:
Suppliers requested to express an interest and shall be subject to meeting Balfour Beatty Rail’s pre-qualification criteria for this package of works.
Appropriate RISQS, Constructionline and Insurances will be required.
Documents shall be issued to those who qualify via Balfour Beatty’s Jaggaer portal. Access shall be supplied to those who qualify.
Responses, including any tender queries, shall be via the Jaggaer portal only.
Response shall be based on best value (commercial and technical) which shall include:
> CVL Test and Commissioning – Scope of Work Schedule.
> Package 3 – TPS Works Information doc ref: TRAN01-KAW-R0-TPS-AAC-Z-CA-000006.