Total quantity or scope of tender
Budget up to £30,000 to include: -
Item Description Rate Qty Type Total
1 Preliminaries
1.1 Health & Safety - 1 item
Method Statements and Risk Assessments
Signage and Separation of Works
1.2 Pre-Tender Site Visit 1 item
A Site visit is required to establish the Electrical and
Mechanical Requirements
1.3 Access Equipment - 1 item
Podiums etc.
-
2 Demolition & Clearance
2.1 Clearance 1 item
Removal of existing equipment and relocate to
Workshop Area
2.2 Removal and Disposal 1 item
Floor Coverings
Suspended Ceiling
Existing Wall Covering and Hygienic Cladding
Existing Plasterboard (Alterations to Electrical)
-
3 Structural & Alterations
3.1 Alterations to Location of the Kitchen Door 1 item -
Remove existing Fire Door Set (Set-Aside for Re-Use
Set-up Protection to Avoid Dust
Cut-out new Opening Location
100mm Dense Blockwork
Lintel
Plaster Repairs
Re-Fit Existing Fire Door Set
Replacement Architraves and Skirting Repairs
-
4 Walls
4.1 New Partitions
4.1.1 Block up Existing Kitchen Door 1 item
Remove existing Fire Door Set and Dispose
100x50mm Frame
75mm Acoustic Insulation
12.5mm Plasterboard
Skirting Repairs
4.1.2 New Wall to Create Washup Area 1 item
100x50mm Frame
Notes: See 5.2 Re: Wall Covering
4.1.3 Partition Over Proposed Door (Cleaners) 1 item
100x50mm Frame
75mm Acoustic Insulation
12.5mm Plasterboard
Plaster Skim
Skirting Repairs
4.1.4 Extend Boxing (Kitchen Waste) 1 item
100x50mm Frame
4.2 WhiteRock Cladding 1 item
Install 12mm Ply to Existing Walls
Base Trim (to Vinyl Coved Upstand)
Joining Trim
Internal & External Corners (Thermally Formed)
3mm Gloss WhiteRock Hygienic Cladding
Thermoformed Internal & External Corners
-
5 Ceilings
5.1 Fire Stopping 1 item
On Removal of the Existing Suspended Ceiling, ensure
that all services and voids are fire stopped utilising -
Intumescent collars
Intumescent Expansion Seals
Fire Rated Boards
As determined from Site Inspection
5.2 Kitchen Areas - 1 item
Hygiene grade Perimeter Trim and Grid
Moisture Resistant (Hygienic Grade) 600x600 Tiles
Frame Work to Create Bulkheads as Required
-
6 Plastering
6.1 Plastering 1 item
Tape Joints
Apply Plaster Skim to the Following Areas -
Blocked Door Kitchen
Over Doorway to Small Store
Allowance for Various Repairs
-
7 Internal Joinery
7.1 Glazed Fire Door 1 item
Door Lining
Glazed Fire Door to Match Existing
Fire Rated Double Action Spring Hinges
Finger Plates and Kick Plates to match Existing
Fire Rated Euro Dead Lock
Double Thumb turn Euro Cylinder
Escutcheon Plates
Intumescent Smoke and Fire Seals
7.2 Fire Door (Store Cupboard) 1 item
Door Lining
Fire Door to Match Existing
Fire Rated Hinges
D' Handle to Match Existing
Fire Rated Euro Dead Lock
Single Euro Cylinder
Escutcheon Plate
Intumescent Smoke and Fire Seals
-
8 Electrical
8.1 Removal - 1 item
Identification of Circuits
Isolation
Disconnection of Appliance for Removal
Remove Face Plates and Surface Wiring
Remove Redundant Services
8.2 Alterations and Additions - 1 item
New Circuits for Appliances
Site Survey Required
Additional Socket Outlets
Design and Install LED Modular Lighting
Design and Install Emergency Lighting
Removal and Re-Installation of Fire Alarm Detection
Cat 6 Data Requirements for Order System
Connection of Appliances
Commission and Testing
-
9 Mechanical
9.1 Disconnection of Existing - 1 item
Remove WC and Basin and Dispose Off Site
Remove Handwash Sink and Sink Units (Set-Aside)
Remove Cleaners Sink (Set-Aside for new location)
Remove Surface Pipework to allow Cladding Works
Remove Redundant Pipework and Dead Legs
9.2 New Installation - 1 item
Install CWM, DHW, Secondary Return and Waste for
the Following Locations -
Note: All Copper with Munson Rings
Cleaners Sink
Prep Area - Sink Unit
Cook Area - Hand Wash
Wash Area - Sink Unit & Dishwasher
Counter Area - Coffee Machine
Hand Wash Sink
9.3 Installation and Connection of The Following 1 item
Isolation Valves and Connections as Required
Cleaners Sink
Prep Area - Sink Unit
Cook Area - Hand Wash
Wash Area - Sink Unit & Dishwasher
Counter Area - Coffee Machine
Hand Wash Sink
-
10 Floor Finishes
10.1 Vinyl Safety Flooring
General Repairs as Required
Latex Self levelling Compound
Altro Walkway 2.5mm Safety Flooring
Fully Welded with Coved Formed Upstands
Main Kitchen Areas 1 item
COSHH / Cleaners Store 1 item
Small Store 1 item
Lobby / Corridor 1 item
Dry Store 1 item
10.2 Carpet Tiles
Remove Existing Covering
Install Space Strobe Carpet Tiles
Admin Office 1 item
-
11 Decoration
11.1 Decoration Requirements - 1 item
All New Copper Pipework
Café - Wall to Blocked Kitchen Door
Cleaners Room
Small Store
Lobby / Corridor
Dry Store
Admin Office
-
12 Other
12.1 Stainless Steel around Oven - 1 item
Supply and Install S-Steel to the Rear and Side of the Oven
12.2 Cleaners Sink - 1 item
Supply and Install WhiteRock Splashback
12.2 Other (Installation Only) 1 item
Fabricated Stainless Steel Units
Note: Allow for Fabrication Drawings for New Bespoke Units
Appliances
Stainless Steel Shelving and Installation
Cleaners Room Spur Shelving and Installation
Dry Store Spur Shelving and Installation
-
Summary
1 Preliminaries
2 Demolition and Clearance
3 Structural and Alterations
4 Walls
5 Ceilings
6 Plastering
7 Joinery
8 Electrical
9 Mechanical
10 Floor Finishes
11 Decoration
12 Other Considerations
Total (Subject to VAT) -
|