CONTRACT NOTICE – OFFICIAL JOURNAL
|
Section I: Contracting Authority
|
I.1)
|
Name, Address and Contact Point(s)
|
|
Radian Group |
Collins House, Bishopstoke Road |
Eastleigh |
SO50 6AD |
UK |
Lowri Willis |
+44 1925282392 |
lwillis@procurementforhousing.co.uk |
|
www.in-tendhost.co.uk/radian/
www.in-tendhost.co.uk/radian/
|
|
|
|

 |
|

 |
|

 |
|
I.2)
|
Type of contracting Authority and Main Activity or Activities
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
|
|
No |
Section II: Object of the Contract
|
II.1)
|
Description
|
II.1.1)
|
Title attributed to the contract by the contracting authorityServicing and Maintenance of Passenger Lifts. |
II.1.2(a))
|
Type of works contract
|
II.1.2(b))
|
Type of supplies contract
|
II.1.2(c))
|
Type of service contract1 |
II.1.2)
|
Main site or location of works, place of delivery or performance
|
II.1.3)
|
This notice involves
|
 |
|
 |
|
 |
|
II.1.4)
|
Information on framework agreement (if applicable)
|
 |
|
 |
|
|
Number of participants to the framework agreement envisaged
|
|
Duration of the framework agreement
|
|
Justification for a framework agreement the duration of which exceeds four years
|
|
Estimated total value of purchases for the entire duration of the framework agreement
|
|
Frequency and value of the contracts to be awarded |
II.1.5)
|
Short description of the contract or purchase(s)
The Works covered by this Contract comprise of a comprehensive all-inclusive servicing and preventive maintenance contract for approximately 75 lifts of different types and manufacture.
The works comprise of the following;
— Regular and routine service visits as per service schedule.
— Provision of a 24/7 call out service for emergencies and breakdowns.
— Carrying out all adjustments, repairs and replacement of parts in accordance with the contract.
— Design work in relation to repairs and replacement parts.
— Adaption's necessary to permit the fitting of new components.
— Carrying out an LG1 Yearly inspection to each lift.
— Lubricants and cleaning materials.
— Conducting formal inspections as scheduled or requested.
— Surveys and associated works appropriate to the project.
— Cleaning of all plant and the respective machine rooms, shafts and other directly related machinery spaces.
— Site & Contract Supervision, including site visits by Qualified Technical staff, Supervisors and Managers as requested.
— Attendance at Contract Review meetings by supervisor and senior manager
— Preparation and issue of reports as detailed.
— Management of all health and safety issues, including CDM.
— Activities, designs, materials and work undertaken to meet industry regulations, formal standards and codes of practice.
— The full requirements of this project documentation as prepared and assembled by Cook and Associates.
|
II.1.6)
|
Common Procurement Vocabulary (CPV)
|
|
|
|
50750000 |
|
|
|
|
|
II.1.7)
|
Contract covered by the Government Procurement Agreement (GPA) |
II.1.8)
|
Division into lots No |
II.1.9)
|
Will variants be accepted
No |
II.2)
|
Quantity or Scope of the Contract
|
II.2.1)
|
Total quantity or scopeThe Works covered by this Contract comprise of a comprehensive all-inclusive servicing and preventive maintenance contract for approximately 75 lifts of different types and manufacture.
The works comprise of the following;
— Regular and routine service visits as per service schedule.
— Provision of a 24/7 call out service for emergencies and breakdowns.
— Carrying out all adjustments, repairs and replacement of parts in accordance with the contract.
— Design work in relation to repairs and replacement parts.
— Adaption's necessary to permit the fitting of new components.
— Carrying out an LG1 Yearly inspection to each lift.
— Lubricants and cleaning materials.
— Conducting formal inspections as scheduled or requested.
— Surveys and associated works appropriate to the project.
— Cleaning of all plant and the respective machine rooms, shafts and other directly related machinery spaces.
— Site & Contract Supervision, including site visits by Qualified Technical staff, Supervisors and Managers as requested.
— Attendance at Contract Review meetings by supervisor and senior manager
— Preparation and issue of reports as detailed.
— Management of all health and safety issues, including CDM.
— Activities, designs, materials and work undertaken to meet industry regulations, formal standards and codes of practice.
— The full requirements of this project documentation as prepared and assembled by Cook and Associates. |
|
600 000630 000 GBP |
II.2.2)
|
OptionsTwo, one year extension periods, following initial three year term, subject to satisfactory performance. |
|
Provisional timetable for recourse to these options36 |
|
Number of possible renewals
|
|
In the case of renewable supplies or service contracts, estimated time frame for subsequent contracts2 |
II.3)
|
Duration of the contract or limit for completion60 |
Section III: Legal, Economic, Financial and Technical Information
|
III.2)
|
Conditions for Participation
|
III.2.1)
|
Personal situation of economic operators, including requirements relating to enrolment on professional or trade registers
As detailed within the tender documentation.
|
III.2.2)
|
Economic and financial capacity
As detailed within the tender documentation.
As detailed within the tender documentation.
|
III.2.3)
|
Technical capacity
As detailed within the tender documentation.
As detailed within the tender documentation.
|
III.2.4)
|
Reserved contracts
|
 |
|
 |
|
III.3)
|
Conditions Specific to Service Contracts
|
III.3.1)
|
Is provision of the service reserved to a specific profession? No |
III.3.2)
|
Will legal entities be required to state the names and professional qualifications of the personnel responsible for the execution of the service? No |
Section IV: Procedure
|
IV.1)
|
Type of Procedure
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
Justification for the choice of accelerated procedure
|
IV.1.1)
|
Have candidates already been selected? No |
IV.1.2)
|
Limitations on the number of operators who will be invited to tender or to participate6 |
|
|
Objective criteria for choosing the limited number of candidates
|
IV.1.3)
|
Reduction of the number of operators during the negotiation or dialogue
|
 |
|
IV.2)
|
Award Criteria
|
|
No
|
|
|
|
Yes
|
|
No
|
IV.2.2)
|
An electronic auction will be used No
|
IV.3 Administrative Information
|
IV.3.1)
|
Reference number attributed to the notice by the contracting authority
P/RAD 0281
|
IV.3.2)
|
Previous publication(s) concerning the same contract
|
 |
|
 |
Other previous publications
|
IV.3.3)
|
Conditions for obtaining specifications and additional documents 01-02-2016
|
IV.3.4)
|
Time-limit for receipt of tenders or requests to participate 07-02-2016 |
IV.3.5)
|
Date of dispatch of invitations to tender or to participate to selected candidates
|
IV.3.6)
|
Language or languages in which tenders or requests to participate can be drawn up
|
IV.3.7)
|
Minimum time frame during which the tenderer must maintain the tender
|
IV.3.8)
|
Conditions for opening tenders
|
|
|
|
8-2-2016
12:00
|
Section VI: Other Information
|
VI.1)
|
Indicate whether this procurement is a recurrent one and the Estimated timing for further notices to be published
|
VI.2)
|
Does the contract relate to a Project/Programme financed by Community Funds? No
|
VI.3)
|
Additional Information
To obtain documentation please go to https://in-tendhost.co.uk/radian/aspx/Home
All questions regarding this tender activity should be directed vya https://in-tendhost.co.uk/radian/aspx/Home
|
VI.4)
|
Procedures for appeal
|
VI.4.1)
|
Body responsible for appeal procedures
|
|
|
|
|
|
|
|
|
|
|
|
Body responsible for mediation procedures
|
|
|
|
|
|
|
|
|
|
VI.4.2)
|
Lodging of appeals
|
VI.4.3)
|
Service from which information about the lodging of appeals may be obtained
|
|
|
|
|
|
|
|
|
|
VI.5)
|
Dispatch date of this Notice 07-01-2016 |