II.2.2) Additional CPV code(s)
45251120
71310000
71311000
71311300
09310000
II.2.3) Place of performance
NUTS code:
00
Main site or place of performance:
Zambia — located on the Zambezi River in the Western Province of Zambia close to the township of Sioma, some 345 km upstream of the Victoria Falls and 120 km upstream of Sesheke.
II.2.4) Description of the procurement
The Owner's Engineer will provide technical assistance and advisory services during the procurement of the EPC Contractor (and separately the M&E contractor) up until financial close of the Project, and at Owner's option during the construction phase. This will include:
— Reviewing relevant background documents relating to the project and the procurement strategy,
— Assisting in the shortlisting of candidates,
— Carrying out a technical review of tenderers outline solutions,
— Participating in dialogues with tenderers,
— Assisting in the tender evaluation and contract award,
— Assisting in the negotiations and finalisation of the EPC contract and completion of the schedules to the EPC contract,
— Environmental and social involvement,
— Responding to Lenders' questions with regard to the EPC Contract, and liaising with Lenders' Technical Advisor, and
— Advising and providing ongoing assistance during construction and the defects liability period, if requested among other things, as further described in the Descriptive Document.
The duration of the Owner's Engineer consultancy services agreement is indicative and is subject to the needs of and timetable for the Project. It is anticipated that initial involvement during procurement of the EPC and M&E contractors will last up to 18 months. The estimated contract value in Sections II.1.5) and II.2.6) is for this period only, and does not include construction-period services.
At owner's option, Owner's Engineer will provide technical assistance and advisory services during the construction phase.
The construction period is anticipated to last approximately 3 years, with an additional 1-2 years depending on length of defects liability period.
Procurement of the EPC contractor and separately a short list of mechanical and electrical contractors will follow the competitive dialogue process. The winning EPC contractor will be responsible for complete procurement of all works and services related to the EPC contract, including mechanical and electrical, and inter-connection.
Further details are set out in the Descriptive Document.
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.6) Estimated value
Value excluding VAT:
350 000.00
USD
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Start:
15/04/2016
End:
31/10/2017
This contract is subject to renewal: No
II.2.9) Information about the limits on the number of candidates to be invited
Envisaged number of candidates: 5
Objective criteria for choosing the limited number of candidates:
As set out in the Pre-qualification Questionnaire.
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
OE tender will provide a proposal for both: (i) EPC contractor selection, EPC contract negotiation and services up to financial close, and (ii) construction period. Provision of services for construction period is at Western Power's option. WP is free to tender for the provision of services during the construction phase by a third party or to select the existing provider to provide such services.
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
II.2.14) Additional information
Estimated contract value in Sections II.1.5) and II.2.6) is for this period only, and does not include construction-period services.
Duration in Section II.2.7) is for the period to financial close only. Involvement in the construction phase is expected to be approximately 3 years plus an additional 2 years for the defects liability period.