Contract Award Notice

Environmental and Social Advisory Services for a 50MW Wind Power Project in Ghana.

  • First published: 12 January 2017
  • Last modified: 12 January 2017
  • Version: N/A
  •  

  • This file may not be fully accessible.

  •  

Information icon

The buyer is not using this website to administer the notice.

To record your interest or obtain additional information or documents please find instructions within the Full Notice Text. (NOTE: Contract Award Notices and Prior Information Notices do not normally require a response)

Contents

Summary

OCID:
Published by:
eleQtra Limited
Authority ID:
AA45373
Publication date:
12 January 2017
Deadline date:
-
Notice type:
Contract Award Notice
Has documents:
No
Has SPD:
No
Has Carbon Reduction Plan:
N/A

Abstract

EleQtra wishes to procure a consulting firm (the ‘Consultant’) to undertake a comprehensive Environment and Social Impact Assessment (‘ESIA’).

In order to evaluate possible environmental and social impacts and to establish a comprehensive management plan to manage and mitigate the identified impacts, the Services to be provided by the Consultant will be carried out over three phases, as follows:

Phase 1: Project Scoping

Undertake an environmental and social scoping study of the Project and draft the Environment and Social Scoping Report and the associated ESIA Terms of Reference (ESIA-TOR). The purpose of scoping is to identify the main potential adverse and beneficial impacts associated with the Project that will be assessed in more detail during Phase 2.

Commence stakeholder engagement and develop an initial Stakeholder Engagement Plan (‘SEP’) for the Project.

Identify the main potential constraints on the Project foot print and develop a constraints map, analysis of which will feed into the technical studies undertaken to define the project footprint to be assessed at Phase 2.

The work beyond Phase 1 shall only proceed after acceptance of the Scoping Report and ESIA-TOR by the Environmental Protection Agency of Ghana (the ‘EPA’).

Phase 2: Environment and Social Impact Assessment

Undertake a comprehensive ESIA of the Project based on the approved ESIA-TOR in compliance with:

— All relevant Ghanaian Laws including the Environmental Protection Agency Act 1994, Act 490 and Ghana Environmental Assessment Regulations 1999;

— The 2012 IFC Performance Standards on Social & Environmental Sustainability;

— The World Bank Group Environmental, Health, and Safety General Guidelines (April 2007a);

— The World Bank Group Environmental, Health, and Safety Guidelines for Wind Energy (August 2015);

— The World Bank Group Environmental, Health, and Safety Guidelines for Transmission Line (if relevant); and

— The Overseas Private Investment Corporation Environmental Guidance Renewable Energy — Wind Projects (January 2012);

— Stakeholder Engagement Standard AA1000(SES).

The ESIA will include a Non-Technical Summary, a characterisation of the environmental and social baseline and a comprehensive assessment of Project impacts, an Environmental and Social Management and Monitoring Plan (‘ESMMP’), a Land Acquisition and Compensation Plan (‘LACP’) and a final SEP.

Phase 3: provide assistance with Financing.

Assist in answering due diligence questions related to environmental and social issues, from potential investors/lenders in the Project. This is a post-ESIA activity and bidders are requested to submit hourly rates for identified staff for this Phase. Procurement of these services will be carried out on a needs basis.

The above Services shall be procured together but may called down in sequence. The Consultant shall not commence work on any Phase of work until instructed to do so by eleQtra.

In the event that a request to proceed to Phase 2 or 3, as the case may be, is not issued by eleQtra, work shall not commence on Phase 2 or 3, and eleQtra accepts no liability whatsoever for Services rendered or costs otherwise incurred beyond Phase 1, or Phase 2 as the case may be.

Further details are set out in the Invitation to Tender.

Full notice text

Contract award notice

Results of the procurement procedure

Section I: Contracting authority

I.1) Name and addresses

eleQtra limited

Eastgate House, 16-19 Eastcastle Street

London

W1W 8DA

UK

Contact person: Richard Avery and Oliver Johnson

Telephone: +44 2070793070

E-mail: richard.avery@eleqtra.com

NUTS: UKI

Internet address(es)

Main address: http://www.eleqtra.com

Address of the buyer profile: http://www.mytenders.org/search/Search_AuthProfile.aspx?ID=AA35589

I.2) Joint procurement

The contract is awarded by a central purchasing body

I.4) Type of the contracting authority

Other: commercial entity voluntarily complying with the Public Contracts Regulations 2015

I.5) Main activity

Other: Project Development Company developing infrastructure

Section II: Object

II.1) Scope of the procurement

II.1.1) Title

Environmental and Social Advisory Services for a 50MW Wind Power Project in Ghana.

II.1.2) Main CPV code

71313440

 

II.1.3) Type of contract

Services

II.1.4) Short description

EleQtra is looking to engage the services of a qualified and experienced environmental and social consulting firm to complete a Scoping Study, Environmental and Social Impact Assessment and to provide assistance with the financing of 50MW Wind Power Project in Ghana. Further details can be found in the Invitation to Tender.

II.1.6) Information about lots

This contract is divided into lots: No

II.1.7) Total value of the procurement

Value excluding VAT: 230 627.00  USD

II.2) Description

II.2.2) Additional CPV code(s)

71313400

71313430

II.2.3) Place of performance

NUTS code:

00


Main site or place of performance:

Ada West and Ada East Districts, Greater Accra, Ghana.

II.2.4) Description of the procurement

EleQtra wishes to procure a consulting firm (the ‘Consultant’) to undertake a comprehensive Environment and Social Impact Assessment (‘ESIA’).

In order to evaluate possible environmental and social impacts and to establish a comprehensive management plan to manage and mitigate the identified impacts, the Services to be provided by the Consultant will be carried out over three phases, as follows:

Phase 1: Project Scoping

Undertake an environmental and social scoping study of the Project and draft the Environment and Social Scoping Report and the associated ESIA Terms of Reference (ESIA-TOR). The purpose of scoping is to identify the main potential adverse and beneficial impacts associated with the Project that will be assessed in more detail during Phase 2.

Commence stakeholder engagement and develop an initial Stakeholder Engagement Plan (‘SEP’) for the Project.

Identify the main potential constraints on the Project foot print and develop a constraints map, analysis of which will feed into the technical studies undertaken to define the project footprint to be assessed at Phase 2.

The work beyond Phase 1 shall only proceed after acceptance of the Scoping Report and ESIA-TOR by the Environmental Protection Agency of Ghana (the ‘EPA’).

Phase 2: Environment and Social Impact Assessment

Undertake a comprehensive ESIA of the Project based on the approved ESIA-TOR in compliance with:

— All relevant Ghanaian Laws including the Environmental Protection Agency Act 1994, Act 490 and Ghana Environmental Assessment Regulations 1999;

— The 2012 IFC Performance Standards on Social & Environmental Sustainability;

— The World Bank Group Environmental, Health, and Safety General Guidelines (April 2007a);

— The World Bank Group Environmental, Health, and Safety Guidelines for Wind Energy (August 2015);

— The World Bank Group Environmental, Health, and Safety Guidelines for Transmission Line (if relevant); and

— The Overseas Private Investment Corporation Environmental Guidance Renewable Energy — Wind Projects (January 2012);

— Stakeholder Engagement Standard AA1000(SES).

The ESIA will include a Non-Technical Summary, a characterisation of the environmental and social baseline and a comprehensive assessment of Project impacts, an Environmental and Social Management and Monitoring Plan (‘ESMMP’), a Land Acquisition and Compensation Plan (‘LACP’) and a final SEP.

Phase 3: provide assistance with Financing.

Assist in answering due diligence questions related to environmental and social issues, from potential investors/lenders in the Project. This is a post-ESIA activity and bidders are requested to submit hourly rates for identified staff for this Phase. Procurement of these services will be carried out on a needs basis.

The above Services shall be procured together but may called down in sequence. The Consultant shall not commence work on any Phase of work until instructed to do so by eleQtra.

In the event that a request to proceed to Phase 2 or 3, as the case may be, is not issued by eleQtra, work shall not commence on Phase 2 or 3, and eleQtra accepts no liability whatsoever for Services rendered or costs otherwise incurred beyond Phase 1, or Phase 2 as the case may be.

Further details are set out in the Invitation to Tender.

II.2.5) Award criteria

Quality criterion: Technical / Weighting: 40

Price / Weighting:  60

II.2.11) Information about options

Options: No

II.2.13) Information about European Union funds

The procurement is related to a project and/or programme financed by European Union funds: No

II.2.14) Additional information

Contract value in section II.2.6 is an estimate only.

Duration of the assignment may vary and may be longer or shorter than the time scale given in II.2.7.

Section IV: Procedure

IV.1) Description

IV.1.1) Type of procedure

Open procedure

IV.1.8) Information about Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: No

IV.2) Administrative information

IV.2.1) Previous publication concerning this procedure

Notice number in the OJ S:

2016/S 195-351349

Section V: Award of contract

A contract/lot is awarded: Yes

V.2 Award of contract

V.2.1) Date of conclusion of the contract

06/01/2017

V.2.2) Information about tenders

Number of tenders received: 10

The contract has been awarded to a group of economic operators: No

V.2.3) Name and address of the contractor

Environmental Resources Management Limited

1-2 Eaton House. Wallbrook Court, North Hinksey Lane

Oxford

OX2 OUS

UK

Telephone: +44 7766166633

NUTS: UKJ14

The contractor is an SME: No

V.2.4) Information on value of the contract/lot (excluding VAT)

Total value of the contract/lot: : 230 627.00  USD

V.2.5) Information about subcontracting

Section VI: Complementary information

VI.3) Additional information

For copies of the Invitation to Tender please access the share file at https://eleqtra.sharefile.com

and use the following login and password:

login: GhanaWindESIA@eleQtra.com

password: GhanaWindESIA2016

Upon downloading the ITT; if you would like to receive information about any clarification log (if the need arises for a clarification log) please contact Richard Avery at richard.avery@eleqtra.com to register your contact details.

eleQtra receives public funds through a grant from the Technical Assistance Facility (‘TAF’) made available through the Private Infrastructure Development Group (‘PIDG’) Trust. It is PIDG's policy that the recipient of its funding must comply with EU law (principally EU Directive 2014/24/EU (the ‘Procurement Directive’)) as though they are ‘Contracting Authorities’, but with some limited flexibility. Neither PIDG Trust nor eleQtra are strictly ‘Contracting Authorities’ for the purposes of the Procurement Directive however, eleQtra is acting as a volunteer in following the UK Public Contract Regulations (SI 2006/5) in complying with PIDG's procurement policy.

In undertaking this procurement eleQtra intends to comply with best practice and EU core principles.

Submission of completed Tenders constitutes acceptance of the provisions of this document

(MT Ref:190356).

VI.4) Procedures for review

VI.4.1) Review body

n/a

London

UK

VI.5) Date of dispatch of this notice

10/01/2017

Coding

Commodity categories

ID Title Parent category
71313440 Environmental Impact Assessment (EIA) services for construction Environmental engineering consultancy services
71313400 Environmental impact assessment for construction Environmental engineering consultancy services
71313430 Environmental indicators analysis for construction Environmental engineering consultancy services

Delivery locations

ID Description
100 UK - All

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

About the buyer

Main contact:
richard.avery@eleqtra.com
Admin contact:
N/a
Technical contact:
N/a
Other contact:
N/a

Further information

Date Details
No further information has been uploaded.

0800 222 9004

Lines are open 8:30am to 5pm Monday to Friday.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.