Contract Award Notice

ITT238 Waterside Campus Energy Centre.

  • First published: 22 July 2016
  • Last modified: 22 July 2016
  • Version: N/A
  •  

  • This file may not be fully accessible.

  •  

Information icon

The buyer is not using this website to administer the notice.

To record your interest or obtain additional information or documents please find instructions within the Full Notice Text. (NOTE: Contract Award Notices and Prior Information Notices do not normally require a response)

Contents

Summary

OCID:
Published by:
The University of Northampton
Authority ID:
AA23382
Publication date:
22 July 2016
Deadline date:
-
Notice type:
Contract Award Notice
Has documents:
No
Has SPD:
No
Has Carbon Reduction Plan:
N/A

Abstract

The University is embarking on a programme to create a wholly new campus on a brown field site providing state-of-the-art facilities and technology that will ensure all students have access to extensive and high-quality teaching facilities, library, lT suites, studios, innovative learning spaces, laboratories, residential accommodation and social facilities. These do not form part of this procurement.

The new campus will comprise higher education buildings, student halls of residence, energy centre (the Energy Centre) and fallow space available for leisure, retail, commercial development and University future expansion. The overall campus development is being delivered through a number of packages of work, of which the Energy Centre is 1 specific package/contract. The University has appointed an infrastructure contractor whose scope includes the design, build and installation of the below ground services and roads inclusive of the district heating network to a point on the boundary of the Energy Centre site area.

The University has appointed a separate academic and public realm contractor to deliver the academic buildings and to take overall main/principal contractor responsibility for the shared construction areas. A separate procurement exercise is currently under way for the design and construction of 1 200 student residences.

The Energy Centre will be located at the Waterside Development Site, Northampton. The land where the Energy Centre is to be built is owned by the University and can be found at the far southern end of North/South Road. The site boundary is bordered by a car park access road to the north, a campus road to the east, an electrical substation and ownership boundary to the south, and a surface car park to the west.

The scope of works for the Energy Centre contract will include:

— Design and construction of an energy centre building on a brownfield site with associated service yard;

— Design, procure, install and set to work heat generation and associated plant as required to supply and maintain the low temperature hot water (LTHW) district heating network;

— Connection to all required incoming services from locations in near proximity to the Energy Centre site boundary including data connections back to the plant rooms in each of the academic and student residential buildings;

— Design and installation of all signage to the building;

— The Energy Centre contractor will be responsible for raising the site levels from the remediation level to the finished level, and installation of associated hard and soft landing;

— Maintenance, operation and campus commissioning support from practical completion (‘PC’) in June 2017 until September 2018, when the University welcomes its first student intake;

— Defects liability period extending from PC in June 2017 to 31.8.2019;

— Management of the discharge of planning conditions;

— Liaison with building control throughout the project duration to obtain building regulations approval;

— Training of University staff both at PC in June 2017 and the student intake in September 2018; and

— Completion and handover of completed Health and Safety file in accordance with the University's requirements.

The Energy Centre contractor will be required to complete the design from the end of RIBA Stage 3 and deliver a fully operational Energy Centre by June 2017, for use by other contractors to test and commission their buildings. Practical completion of the works will be granted at this point.

The Energy Centre contractor will appoint a design team to complete the technical design from the end of RIBA stage 3. Should the Energy Centre contractor wish to approach the client design team directly to carry out this design work, they may do so.

The Energy Centre contractor will then remain on site under the terms of the NEC3 form of design and build contract (in the form to be issu

Full notice text

CONTRACT AWARD NOTICE – OFFICIAL JOURNAL

Section I: Contracting Authority

I.1)

Name, Address and Contact Point(s)


The University of Northampton

Park Campus, Boughton Green Road

Northampton

NN2 7AL

UK

NUTS Code (UK23)

Julia Gough

+44 1604892663

julia.gough@northampton.ac.uk

+44 1604722106

http://www.northampton.ac.uk

http://in-tendhost.co.uk/universityofnorthampton/

I.2)

Type of contracting Authority and Main Activity or Activities

Unchecked box
Unchecked box
Unchecked box
Unchecked box
Checked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Unchecked box
Checked box
No

Section II: Object of the Contract

II.1)

Description

II.1.1)

Title attributed to the contract by the contracting authority

ITT238 Waterside Campus Energy Centre.

II.1.2(a))

Type of works contract

Unchecked box Checked box
Unchecked box

II.1.2(b))

Type of supplies contract

II.1.2(c))

Type of service contract

II.1.2)

Main site or location of works, place of delivery or performance

Northampton.


UKF23

II.1.3)

This notice involves a framework agreement

Unchecked box
Unchecked box

II.1.4)

Short description of the contract or purchase(s)

The University is embarking on a programme to create a wholly new campus on a brown field site providing state-of-the-art facilities and technology that will ensure all students have access to extensive and high-quality teaching facilities, library, lT suites, studios, innovative learning spaces, laboratories, residential accommodation and social facilities. These do not form part of this procurement.

The new campus will comprise higher education buildings, student halls of residence, energy centre (the Energy Centre) and fallow space available for leisure, retail, commercial development and University future expansion. The overall campus development is being delivered through a number of packages of work, of which the Energy Centre is 1 specific package/contract. The University has appointed an infrastructure contractor whose scope includes the design, build and installation of the below ground services and roads inclusive of the district heating network to a point on the boundary of the Energy Centre site area.

The University has appointed a separate academic and public realm contractor to deliver the academic buildings and to take overall main/principal contractor responsibility for the shared construction areas. A separate procurement exercise is currently under way for the design and construction of 1 200 student residences.

The Energy Centre will be located at the Waterside Development Site, Northampton. The land where the Energy Centre is to be built is owned by the University and can be found at the far southern end of North/South Road. The site boundary is bordered by a car park access road to the north, a campus road to the east, an electrical substation and ownership boundary to the south, and a surface car park to the west.

The scope of works for the Energy Centre contract will include:

— Design and construction of an energy centre building on a brownfield site with associated service yard;

— Design, procure, install and set to work heat generation and associated plant as required to supply and maintain the low temperature hot water (LTHW) district heating network;

— Connection to all required incoming services from locations in near proximity to the Energy Centre site boundary including data connections back to the plant rooms in each of the academic and student residential buildings;

— Design and installation of all signage to the building;

— The Energy Centre contractor will be responsible for raising the site levels from the remediation level to the finished level, and installation of associated hard and soft landing;

— Maintenance, operation and campus commissioning support from practical completion (‘PC’) in June 2017 until September 2018, when the University welcomes its first student intake;

— Defects liability period extending from PC in June 2017 to 31.8.2019;

— Management of the discharge of planning conditions;

— Liaison with building control throughout the project duration to obtain building regulations approval;

— Training of University staff both at PC in June 2017 and the student intake in September 2018; and

— Completion and handover of completed Health and Safety file in accordance with the University's requirements.

The Energy Centre contractor will be required to complete the design from the end of RIBA Stage 3 and deliver a fully operational Energy Centre by June 2017, for use by other contractors to test and commission their buildings. Practical completion of the works will be granted at this point.

The Energy Centre contractor will appoint a design team to complete the technical design from the end of RIBA stage 3. Should the Energy Centre contractor wish to approach the client design team directly to carry out this design work, they may do so.

The Energy Centre contractor will then remain on site under the terms of the NEC3 form of design and build contract (in the form to be issued with the invitation to Tender) in order to undertake the operation and maintenance of the Energy Centre between June 2017 and September 2018, at which point the University will take responsibility. They will also work with the other main contractors in the commissioning of the buildings and connection to the Energy Centre.

An extended defects liability period will start from award of PC in June 2017 and conclude on 31.8.2019 (The system will be monitored in use during this time to allow seasonal commissioning). This extended period is required to ensure the facility is under a defects liability period for a full academic cycle when the buildings will be in use.

II.1.5)

Common Procurement Vocabulary (CPV)

45251250
45259300
45331110
45233160
45231400
45112700
45232150
45233161
45210000
50700000
45214400
50532300
45251142
45231100
50721000
42160000
45315000
45232141
42515000

II.1.6)

Contract covered by the government procurement agreement (GPA)

Yes

II.2)

Total final value of the contract(s)

II.2.1)

Total final value of the contract(s)

 5 325 465   GBP     

Section IV: Procedure

IV.1)

Type of procedure

IV.1.1)

Type of procedure

IV.2)

Award criteria

IV.2.1)

Award criteria

Unchecked box
Checked box
Contractor's proposed team 10
Management of delivery 5
Pre-construction phase methodology 10
Construction phase methodology 10
Pre-construction phase programme 5
Construction phase programme 10
Health and safety 5
Commentary on pre-planning cost plan 5
Commissioning, working with other contractors, and co-ordination and management of packages 10
Price analysis 30

IV.2.2)

An electronic auction has been used

No

IV.3)

Administrative information

IV.3.1)

File reference number attributed by the contracting authority

ITT238

IV.3.2)

Previous publication(s) concerning the same contract


2015/S 205-371692 22-10-2015

Other previous publications

Section V: Award of contract

V.1)

Date of contract award:

 28-4-2016

V.2)

Numbers of offers received:

3

V.3)

Name and address of economic operator to whom the contract has been awarded


Vital Energi Utilities Ltd

Century House, Roman Road, Lancashire

Blackburn

BB1 2LD

UK

sales@vitalenergi.co.uk

+44 1254296000

www.vitalenergi.co.uk

V.4)

Information on value of contract

 5 000 000 GBP 

V.5)

The contract is likely to be subcontracted

Yes

49

Short description of the value/proportion of the contract to be subcontracted

Section VI: Complementary Information

VI.1)

Contract related to a project and/or programme financed by community funds?

No



VI.2)

Additional Information

VI.3)

Procedures for appeal

VI.3.1)

Body responsible for appeal procedures


University of Northampton

Park Campus, Boughton Green Road

Northampton

NN2 7AL

UK




Body responsible for mediation procedures










VI.3.2)

Lodging of appeals

In accordance with the Public Contracts Regulations 2015 (as amended).

VI.3.3)

Service from which information about the lodging of appeals may be obtained


Cabinet Office








VI.4)

Dispatch date of this Notice

 19-07-2016

Coding

Commodity categories

ID Title Parent category
45331110 Boiler installation work Heating, ventilation and air-conditioning installation work
42160000 Boiler installations Machinery for the production and use of mechanical power
45210000 Building construction work Works for complete or part construction and civil engineering work
50721000 Commissioning of heating installations Repair and maintenance services of central heating
45231400 Construction work for electricity power lines Construction work for pipelines, communication and power lines
45214400 Construction work for university buildings Construction work for buildings relating to education and research
42515000 District heating boiler Heat-exchange units, air-conditioning and refrigerating equipment, and filtering machinery
45251250 District-heating plant construction work Construction works for power plants and heating plants
45315000 Electrical installation work of heating and other electrical building-equipment Electrical installation work
45233161 Footpath construction work Construction, foundation and surface works for highways, roads
45231100 General construction work for pipelines Construction work for pipelines, communication and power lines
45232141 Heating works Ancillary works for pipelines and cables
45259300 Heating-plant repair and maintenance work Repair and maintenance of plant
45112700 Landscaping work Excavating and earthmoving work
45233160 Paths and other metalled surfaces Construction, foundation and surface works for highways, roads
50700000 Repair and maintenance services of building installations Repair and maintenance services
50532300 Repair and maintenance services of generators Repair and maintenance services of electrical machinery, apparatus and associated equipment
45251142 Wood-fired power station construction work Construction works for power plants and heating plants
45232150 Works related to water-distribution pipelines Ancillary works for pipelines and cables

Delivery locations

ID Description
100 UK - All

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

About the buyer

Main contact:
julia.gough@northampton.ac.uk
Admin contact:
N/a
Technical contact:
N/a
Other contact:
N/a

Further information

Date Details
No further information has been uploaded.