Contract Notice

installation of Solar PV, Battery storage and EV charging at domestic dwelling in Bridgend

  • First published: 19 July 2022
  • Last modified: 19 July 2022

Contents

Summary

OCID:
ocds-kuma6s-123226
Published by:
H Factor
Authority ID:
AA80333
Publication date:
19 July 2022
Deadline date:
27 July 2022
Notice type:
Contract Notice
Has documents:
No
Has SPD:
No
Has Carbon Reduction Plan:
N/A

Abstract

Scope Design and Install a Grid Tied 11.0 kWp Photovoltaic Array, 10kWh Battery Storage and 7.2 kW EV Charge Point for Mr. Julian Allen, Fox Hollows, Heol Spencer, Coity, Bridgend, Mid Glamorgan, CF35 6AT. The PV Inverter and Battery to be located within attached garage area. The new EV charge point will be located to side of the attached garage.. PV System Design. The PV system will incorporate the following points within the design. • Inverter must have minimum 12-year warranty • Type 2 surge protection built into the inverter. • Tier 1 Monocrystalline Modules with a Module Efficiency greater than 20% • Modules to have a 12 Year Warranty for Materials and Processing. • Modules to have 25-year Power output Warranty (Power Output Tolerance - ≤2% Year 1 & ≤0.55% years 2 to 25) • Safe Touch voltage technology built into the design to reduce DC voltage at loss of inverter power. • Optimisation to mitigate all types of module mismatch-loss from manufacturing tolerance to partial shading. • Optimisation to ensure maximum generation of the PV modules at panel level, minimum one for two panels. • Inverters and optimisers be manufactured from the same company • Modbus meter with CT’s at intake position to monitor Import / Export via online monitoring system. • For ease of maintenance, module level monitoring is to be included with connection to internet • By isolating the AC supply the DC circuit must reduce below DC touch safe level • Inverter selection must have built in arc fault detection according to UL1699B • Arc fault detection must reduce DC current and DC voltage. • In Roof mounting system. • G99 Application for connection. • MCS registration. Battery System Design The Battery Storage system will incorporate the following points within the design. • DC coupled to PV system. • Battery to be Floor or Wall Mounted. • Expandable up to 30kWh • 10 Year Product Warranty. • 5kW AC Discharge power. EV Charge Point The Electric Vehicle Charge point will incorporate the following in the design. • 1 x Single 7kW Type 2 Mode 3Charge Point. • 3 Charging Modes: ECO, ECO+ & FAST • Optimises Microgeneration Self-Consumption • Works with Solar PV • PIN Code lock Function. • Curtilage Power Management Function • Built in PEN Fault Detection (No Earth Rod Requirements) • Smart Charge Point Regulations 2021 Compliant. • Smart Charge Point Regulations 2021 Compliant. • OZEV approved. • Warranty – Minimum 3 years Electrical Infrastructure A new 4-way 100A Single Phase Consumer Unit will be required for the New Inverter, Charge Point and meter. The existing consumer unit has no spare capacity available. New consumer unit to be connected via 100A connection blocks via incoming supply tails. Access Access to be supplied via scaffold with edge protection to all areas of the roof where proposed PV array is to be installed. Scaffold to have all safety permits and certificates in place before access to work granted. A site visit to site is recommended to confirm design requirements prior to pricing.

Full notice text

CONTRACT NOTICE – NATIONAL

WORKS

1 Authority Details

1.1

Authority Name and Address


H Factor

Technology, Penwaungoch, Pentwyn road,

Treharris

CF46 5BS

UK

Simon Conway

+44 7496843652

spfconway@gmail.com


http://www.sell2wales.gov.wales

1.2

Address from which documentation may be obtained


H Factor

Technology, Penwaungoch, Pentwyn road,

Treharris

CF46 5BS

UK

Simon Conway

+44 7496843652

spfconway@gmail.com

1.3

Completed documents must be returned to:


H Factor

Technology, Penwaungoch, Pentwyn road,

Treharris

CF46 5BS

UK

Simon Conway

+44 7496843652

spfconway@gmail.com

2 Contract Details

2.1

Title

installation of Solar PV, Battery storage and EV charging at domestic dwelling in Bridgend

2.2

Description of the goods or services required

Scope

Design and Install a Grid Tied 11.0 kWp Photovoltaic Array, 10kWh Battery Storage and 7.2 kW EV Charge Point for Mr. Julian Allen, Fox Hollows, Heol Spencer, Coity, Bridgend, Mid Glamorgan, CF35 6AT. The PV Inverter and Battery to be located within attached garage area. The new EV charge point will be located to side of the attached garage..

PV System Design.

The PV system will incorporate the following points within the design.

• Inverter must have minimum 12-year warranty

• Type 2 surge protection built into the inverter.

• Tier 1 Monocrystalline Modules with a Module Efficiency greater than 20%

• Modules to have a 12 Year Warranty for Materials and Processing.

• Modules to have 25-year Power output Warranty (Power Output Tolerance - ≤2% Year 1 & ≤0.55% years 2 to 25)

• Safe Touch voltage technology built into the design to reduce DC voltage at loss of inverter power.

• Optimisation to mitigate all types of module mismatch-loss from manufacturing tolerance to partial shading.

• Optimisation to ensure maximum generation of the PV modules at panel level, minimum one for two panels.

• Inverters and optimisers be manufactured from the same company

• Modbus meter with CT’s at intake position to monitor Import / Export via online monitoring system.

• For ease of maintenance, module level monitoring is to be included with connection to internet

• By isolating the AC supply the DC circuit must reduce below DC touch safe level

• Inverter selection must have built in arc fault detection according to UL1699B

• Arc fault detection must reduce DC current and DC voltage.

• In Roof mounting system.

• G99 Application for connection.

• MCS registration.

Battery System Design

The Battery Storage system will incorporate the following points within the design.

• DC coupled to PV system.

• Battery to be Floor or Wall Mounted.

• Expandable up to 30kWh

• 10 Year Product Warranty.

• 5kW AC Discharge power.

EV Charge Point

The Electric Vehicle Charge point will incorporate the following in the design.

• 1 x Single 7kW Type 2 Mode 3Charge Point.

• 3 Charging Modes: ECO, ECO+ & FAST

• Optimises Microgeneration Self-Consumption

• Works with Solar PV

• PIN Code lock Function.

• Curtilage Power Management Function

• Built in PEN Fault Detection (No Earth Rod Requirements)

• Smart Charge Point Regulations 2021 Compliant.

• Smart Charge Point Regulations 2021 Compliant.

• OZEV approved.

• Warranty – Minimum 3 years

Electrical Infrastructure

A new 4-way 100A Single Phase Consumer Unit will be required for the New Inverter, Charge Point and meter. The existing consumer unit has no spare capacity available. New consumer unit to be connected via 100A connection blocks via incoming supply tails.

Access

Access to be supplied via scaffold with edge protection to all areas of the roof where proposed PV array is to be installed. Scaffold to have all safety permits and certificates in place before access to work granted.

A site visit to site is recommended to confirm design requirements prior to pricing.

NOTE: To register your interest in this notice and obtain any additional information please visit the Sell2Wales Web Site at https://www.sell2wales.gov.wales/Search/Search_Switch.aspx?ID=123226.

2.3

Notice Coding and Classification

09330000 Solar energy
09331200 Solar photovoltaic modules
09332000 Solar installation
31158100 Battery chargers
31422000 Battery packs
34144900 Electric vehicles
1017 Bridgend and Neath Port Talbot

2.4

Total quantity or scope of tender

11KWp PV array

10KW battery

1 EV charging point

3 Conditions for Participation

3.1

Minimum standards and qualification required

MCS accredited installer

Certified to all up to date electrical regs

4 Administrative Information

4.1

Type of Procedure

Single stage

4.2

Reference number attributed to the notice by the contracting authority

SC4

4.3

Time Limits

Time-limit for receipt of completed tenders
    27-07-2022  Time  12:00

Estimated award date
 29-07-2022

4.5

Language or languages in which tenders or requests to participate can be drawn up

EN 

4.6

Tender Submission Postbox

5 Other Information

5.1

Additional Information

N/A

(WA Ref:123226)

Under the terms of this contract the successful supplier(s) will be required to deliver Community Benefits in support of the authority’s economic and social objectives. Accordingly, contract performance conditions may relate in particular to social and environmental considerations. The Community Benefits included in this contract are:

Local generation of renewable energy

Relates to the following project/programme financed by EU Community Funds: AMMV energy Workx project

5.2

Additional Documentation

5.3

Publication date of this notice

 19-07-2022

Coding

Commodity categories

ID Title Parent category
31158100 Battery chargers Chargers
31422000 Battery packs Primary batteries
34144900 Electric vehicles Special-purpose motor vehicles
09330000 Solar energy Electricity, heating, solar and nuclear energy
09332000 Solar installation Solar energy
09331200 Solar photovoltaic modules Solar panels

Delivery locations

ID Description
1017 Bridgend and Neath Port Talbot

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

Document family

Notice details
Publication date:
19 July 2022
Deadline date:
27 July 2022 00:00
Notice type:
Contract Notice
Authority name:
H Factor
Publication date:
09 November 2022
Notice type:
Contract Award Notice
Authority name:
H Factor

About the buyer

Main contact:
spfconway@gmail.com
Admin contact:
spfconway@gmail.com
Technical contact:
N/a
Other contact:
spfconway@gmail.com

Further information

Date Details
21/07/2022 16:00
Site Survey
As this is a domestic dwelling , to avoid disruption to the homeowners we are accepting quotations based on a desktop study using the current google earth picture of the site.

We are aware there may be site specific additional costs (that can only be quantified with a detailed site visit) which will be reviewed with the successful contractor prior to installation start.

Q&A

Ask the buyer any questions you may have relating to this notice. To ask the buyer a question or questions please click the "View Questions and Answers" button.


0800 222 9004

Lines are open 8:30am to 5pm Monday to Friday.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.