II.2.2) Additional CPV code(s)
45211100
45211300
II.2.3) Place of performance
NUTS code:
UKM83
Main site or place of performance:
Johnstone
II.2.4) Description of the procurement
The Works required within the project shall be undertaken on a phased programme of works to enable demolition and site clearance of existing tenements (carried out by the Council) within later phases of the Development. On appointment site A (19 Units) and site B (29 Units) will be available for construction with site D (14 Units) available for construction from January 2019. Site C (26 Units) and site E (7 Units) each have one remaining owner; a Compulsory Purchase Order (CPO) process is underway to obtain ownership to enable site clearance. With Scottish Ministers having approved the CPO, ownership of these properties is expected in January 2019. Allowing for 1 year for site clearance and investigations, access for sites C and E is expected to be January 2019. Whilst it is expected sites C and E will progress and be included within the ITT, the Council reserves the right to reduce or remove these sites should the CPO process be unsuccessful. Alternatively, the Council reserves the right to enter into further discussions with the Principal Contractor in relation to the start date for sites C and E should the CPO process be unsuccessful. Demolition (including foundations) and site clearance of sites C, D and E will be carried out by the Council ahead of site handover.
Works that are required to be undertaken within the project include but are not limited to:
— design and Build of 95 Nº New Build homes,
— novation of the Council’s appointed Design Team,
— completion of Stage 2 warrant process,
— construction of retaining walls,
— external works including driveways, front and back gardens, road and pavement resurfacing,
— utility and Drainage connections,
— installation of kitchen and bathroom fittings,
— accessible use fittings to Wheelchair Bungalow properties, (2 Nº)
— site Investigations of Sites C, D and E,
— considerate Constructor Scheme Compliance,
— engagement with local community, resident groups and school (Open days, Newsletters etc.),
— site security through SIA certified contractor,
— traffic Management (In co-ordination with demolition contractor),
— provide Tenant Manual / Information Pack and Training / Demonstration to tenants and Council staff.
II.2.5) Award criteria
Quality criterion: Quality (questions to be confirmed in Invitation to Tender)
/ Weighting: 60 %
Price
/ Weighting:
40 %
II.2.11) Information about options
Options:
No
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No