Contract Award Notice

Geotechnical Engineering Advisory and Consultancy Services

  • First published: 06 March 2024
  • Last modified: 06 March 2024

The buyer is not using this website to administer the notice.

To record your interest or obtain additional information or documents please find instructions within the Full Notice Text. (NOTE: Contract Award Notices and Prior Information Notices do not normally require a response)

Contents

Summary

OCID:
ocds-h6vhtk-031ebf
Published by:
Thames Water Utilities Limited
Authority ID:
AA20727
Publication date:
06 March 2024
Deadline date:
-
Notice type:
Contract Award Notice
Has documents:
No
Has SPD:
No
Has Carbon Reduction Plan:
N/A

Abstract

Thames Water require highly specialised technical support in the Geotechnical Engineering discipline concerning impacts to our critical trunk sewers, water transfer tunnels and strategic water mains from the impact of third-party construction activities.

Also, expert geotechnical advice and support regarding the analyses of ground movements caused by third-party subsurface construction activity, review of third-party tunnel analyses and design and effect of construction work on structural integrity all existing Thames Water tunnels (both bolted and unbolted construction) .

The geotechnical engineering support will also include but may not necessarily be limited to the assessment on the impact of third-party activities adjacent to tunnels and expert advice on any proposed geotechnical/ structural safety issues that need to be addressed. Support for other engineering impact assessment on other structures may also be required.

Overall, the service will involve providing robust engineering geotechnical assurance to the Business in the implementation of Capital Delivery projects, Developer Services projects.

The scopes of services provided are:

• Inspection of Thames Water Critical Assets such as tunnels and reservoirs for geotechnical engineering stability and recommending remedial action and preparation of the survey guidance procedures currently used across the network.

• Review of complex geotechnical design proposals from developers, national infrastructure, and transport authorities on existing Thames Water assets.

• Carrying out research and investigations programme to identify the causal mechanisms of potential critical assert such as tunnel failures (predictive failures)

• Providing advice to TWUL Reservoir Safety and Asset Condition Manager after review of developer's proposals for works in the vicinity of tunnels, including risk mitigation measures

• Reviewing and reporting on impacts to strategic sewers particularly those under surcharge risk which is now present in most areas of London (e.g., the recent failure of Low-Level No. 1 at Battersea).

• Assisting TWUL during negotiations with Developers (Clients, Architects, Engineers and Contractors.) on complex projects and where appropriate advice on essential risk mitigation works.

• Providing dispute avoidance advisory services to avert possible legal challenges by Developers and External Parties.

•Support Developer Services, Capital Delivery and Tideway Tunnel Integration Teams in geotechnical Risk Assessment and preparation of required reports for project implementation.

Full notice text

Contract award notice – utilities

Section I: Contracting entity

I.1) Name and addresses

THAMES WATER UTILITIES LIMITED

02366661

Reading

RG18DB

UK

Contact person: Thames Water

E-mail: procurement.support.centre@thameswater.co.uk

NUTS: UKJ11

Internet address(es)

Main address: https://www.thameswater.co.uk/

I.6) Main activity

Water

Section II: Object

II.1) Scope of the procurement

II.1.1) Title

Geotechnical Engineering Advisory and Consultancy Services

Reference number: FA1727

II.1.2) Main CPV code

71332000

 

II.1.3) Type of contract

Services

II.1.4) Short description

Thames Water require highly specialised technical support in the Geotechnical Engineering discipline concerning impacts to our critical trunk sewers, water transfer tunnels and strategic water mains from the impact of third-party construction activities.

Also, expert geotechnical advice and support regarding the analyses of ground movements caused by third-party subsurface construction activity, review of third-party tunnel analyses and design and effect of construction work on structural integrity all existing Thames Water tunnels (both bolted and unbolted construction) .

The geotechnical engineering support will also include but may not necessarily be limited to the assessment on the impact of third-party activities adjacent to tunnels and expert advice on any proposed geotechnical/ structural safety issues that need to be addressed. Support for other engineering impact assessment on other structures may also be required.

Overall, the service will involve providing robust engineering geotechnical assurance to the Business in the implementation of Capital Delivery projects, Developer Services projects.

The scopes of services provided are:

• Inspection of Thames Water Critical Assets such as tunnels and reservoirs for geotechnical engineering stability and recommending remedial action and preparation of the survey guidance procedures currently used across the network.

• Review of complex geotechnical design proposals from developers, national infrastructure, and transport authorities on existing Thames Water assets.

• Carrying out research and investigations programme to identify the causal mechanisms of potential critical assert such as tunnel failures (predictive failures)

• Providing advice to TWUL Reservoir Safety and Asset Condition Manager after review of developer's proposals for works in the vicinity of tunnels, including risk mitigation measures

• Reviewing and reporting on impacts to strategic sewers particularly those under surcharge risk which is now present in most areas of London (e.g., the recent failure of Low-Level No. 1 at Battersea).

• Assisting TWUL during negotiations with Developers (Clients, Architects, Engineers and Contractors.) on complex projects and where appropriate advice on essential risk mitigation works.

• Providing dispute avoidance advisory services to avert possible legal challenges by Developers and External Parties.

•Support Developer Services, Capital Delivery and Tideway Tunnel Integration Teams in geotechnical Risk Assessment and preparation of required reports for project implementation.

II.1.6) Information about lots

This contract is divided into lots: No

II.1.7) Total value of the procurement

Lowest offer:   / Highest offer:  

II.2) Description

II.2.3) Place of performance

NUTS code:

UKH

UKI

II.2.4) Description of the procurement

Thames Water require highly specialised technical support in the Geotechnical Engineering discipline concerning impacts to our critical trunk sewers, water transfer tunnels and strategic water mains from the impact of third-party construction activities.

Also, expert geotechnical advice and support regarding the analyses of ground movements caused by third-party subsurface construction activity, review of third-party tunnel analyses and design and effect of construction work on structural integrity all existing Thames Water tunnels (both bolted and unbolted construction) .

The geotechnical engineering support will also include but may not necessarily be limited to the assessment on the impact of third-party activities adjacent to tunnels and expert advice on any proposed geotechnical/ structural safety issues that need to be addressed. Support for other engineering impact assessment on other structures may also be required.

Overall, the service will involve providing robust engineering geotechnical assurance to the Business in the implementation of Capital Delivery projects, Developer Services projects.

The scopes of services provided are:

• Inspection of Thames Water Critical Assets such as tunnels and reservoirs for geotechnical engineering stability and recommending remedial action and preparation of the survey guidance procedures currently used across the network.

• Review of complex geotechnical design proposals from developers, national infrastructure, and transport authorities on existing Thames Water assets.

• Carrying out research and investigations programme to identify the causal mechanisms of potential critical assert such as tunnel failures (predictive failures)

• Providing advice to TWUL Reservoir Safety and Asset Condition Manager after review of developer's proposals for works in the vicinity of tunnels, including risk mitigation measures

• Reviewing and reporting on impacts to strategic sewers particularly those under surcharge risk which is now present in most areas of London (e.g., the recent failure of Low-Level No. 1 at Battersea).

• Assisting TWUL during negotiations with Developers (Clients, Architects, Engineers and Contractors.) on complex projects and where appropriate advice on essential risk mitigation works.

• Providing dispute avoidance advisory services to avert possible legal challenges by Developers and External Parties.

•Support Developer Services, Capital Delivery and Tideway Tunnel Integration Teams in geotechnical Risk Assessment and preparation of required reports for project implementation.

II.2.11) Information about options

Options: No

II.2.13) Information about European Union funds

The procurement is related to a project and/or programme financed by European Union funds: No

Section IV: Procedure

IV.1) Description

IV.1.1) Type of procedure

Negotiated with call for competition

IV.1.8) Information about Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: No

IV.2) Administrative information

IV.2.1) Previous publication concerning this procedure

Notice number in the OJ S:

2022/S 000-006182

Section V: Award of contract

A contract/lot is awarded: No

V.1 Information on non-award

Section VI: Complementary information

VI.3) Additional information

We refer to the above procurement for Geotechnical Engineering Advisory Service at Thames Water.

Please note that we have taken the decision not to proceed with this procurement. This project has been "On Hold" for several months due to internal considerations.

During this period, we have taken the opportunity to thoroughly review our requirements and as a result, we have concluded that a revised specification is necessary to align with our evolving priorities.

We will look to restart the procurement process once we have reviewed and agreed new specification, but we cannot give any indication currently of when that might be. We advertise opportunities via the Government's Find A Tender website, so please look out here for anything new that may be of interest: https://www.find-tender.service.gov.uk/

Thank you for your interest in this procurement.

VI.4) Procedures for review

VI.4.1) Review body

Thames Water Utilities Limited

Reading

UK

VI.5) Date of dispatch of this notice

05/03/2024

Coding

Commodity categories

ID Title Parent category
71332000 Geotechnical engineering services Miscellaneous engineering services

Delivery locations

ID Description
100 UK - All

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

About the buyer

Main contact:
procurement.support.centre@thameswater.co.uk
Admin contact:
N/a
Technical contact:
N/a
Other contact:
N/a

Further information

Date Details
No further information has been uploaded.

0800 222 9004

Lines are open 8:30am to 5pm Monday to Friday.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.