Description of the contract
This tender publictation is seeking sub-contractor work: CONCRETE SLABS – the supply and placement of all materials associated with the concrete slabs construction, including all necessary plant and equipment to carry out the works, i.e. concrete, mesh, corrugated steel decking, shuttering/formwork, edge protection, access equipment, concrete pumps, power-floats & finishing tools/equipment etc. Sub-contractor to satisfy themselves that they have allowed for all necessary access and equipment in order to carry out the works including being aware of site conditions that may have an effect on completing the works to schedule as per programme attached.
Note:
• Sub-contractor welcome to include alternate design & costings in addition to pricing scheduled items
• Minor engineering should be allowed for by the sub-contractor
• Design coordination with the project Architect, Engineers & Cladding specialist
• Sub-contractor should allow all necessary temporary access associated with the works
• Site visit is compulsory to appreciate the clients existing working environment
• Sub-contractor to allow for task lighting and power for the duration of their works
• Sub-contractor to allow for material storage within price (as required)
• Onsite WC and mess facilities are available ‘por gratis’
Costs:
Your lowest quotation is invited for the sub-contract work shown above inclusive of all Design, Labour, Plant and Materials, in accordance with the following documents: -
Specification (pages) : Included on drawings
Drawings:
Slab Info;
Roger Casey Drawings: 19895-102_2018-03-20
Roger Casey Drawings: 19895-201, 19895-202 & 19895-215 Preliminary-2018_04_03
Powell Dobson Drawing: 17055 (P) 103
Other Scheme Drawings;
Roger Casey Drawings: 19895-01
Roger Casey Drawings: 19895-100_2018-03-20
Roger Casey Drawings: 19895-101_2018-03-20
Roger Casey Drawings: 19895-203, 204, 205, 206, 210, 211 & 220
Powell Dobson Drawing: 01 Cold Store Sketch
Powell Dobson Drawing: 17055 (P) 104, 105, 106, 107, 108, 109, 110, 111, 112, 113, 114 & 115.
Powell Dobson Drawings: 17055 (SK) 003
Powell Dobson Drawings: 17055 (EX) 01, 02 & 03
Project Boundary Drawing – Amended PDA 17055 (P)101
Other: Puffin 04 – Pictures 1, 2 and 4
Timescale: Enquiry Programme attached, it is envisaged that out of hours works will be required and must be included within your rates.
Subcontract Particulars: None
FLUCTUATIONS: Fixed Price for Duration
DAYWORK: Please identify your hourly (all-inclusive) rate for all labour and plant costs, together with %mark-up required to the nett
DISCOUNT: Please clearly state within your quotation the main contractors discount being offered
By submitting a quotation it is deemed that you have inspected the drawings and visited the site to obtain any relevant details. Extras will not be paid due to lack of knowledge of the site conditions or form of general construction details.
Contract Conditions:
Liquidated Damages - £2,000 per week or part thereof
Rectification Period - 6 Months
Retention Percentage - 3%
Contractor’s Insurance Cover - 5,000,000
Insurance Liability of Employer - 10,000,000
|