Description of risks to contract performance
• The future requirements for the refurbishment, redevelopment, partial retention or potential selective demolition of heritage assets within the regeneration area may evolve as further surveys, technical investigations, viability assessments and planning discussions are undertaken, particularly in relation to the Engine Works and other historic buildings.
• The scope, timing and extent of enabling infrastructure works may require amendment following the completion of further technical investigations, including sewer diversion requirements, utilities infrastructure, ground conditions and site preparation works.
• The regeneration programme may be affected by the availability, timing, conditions or reallocation of public sector grant funding, including Towns Fund, Brownfield Land Release Fund and other funding opportunities which may become available during the term of the Development Agreement.
• The proposed NHS Community Diagnostics Centre may proceed, be amended or not proceed, which could require changes to site boundaries, development parcels, infrastructure requirements, car parking provision, development phasing and associated obligations.
• Additional land and property interests within the wider Shrub Hill Quarter may be acquired by the Authority or become available during the term of the Development Agreement, requiring amendments to the scope of the partnership and development programme.
• The extent and timing of development parcels may require amendment to reflect planning requirements, viability considerations, market conditions, stakeholder requirements or changes to the agreed phasing strategy.
• Additional public realm, transport, active travel, rail connectivity, environmental or infrastructure requirements may emerge through the planning process, engagement with statutory consultees or funding bodies, or through the evolution of the wider masterplan.
• The long-term regeneration strategy may require modification to respond to changes in national, regional or local planning policy, funding programmes, transport initiatives or Local Government Reorganisation arrangements impacting the project area.
The Authority considers that these risks may jeopardise the performance of the contract but, due to the nature of the risks, due to the long-term nature and complexity of the regeneration project, the precise nature and extent of any resulting changes cannot reasonably be determined at the time of contract award . Therefore, the Authority reserves the right to modify the awarded contract to address the risks in accordance with Schedule 8 of the Act.