1
Is the total value above threshold?
Below threshold
Date the contract will be signed (estimated)
05 November 2026, 00:00AM Contract dates (estimated)
05 November 2026, 00:00AM to 31 August 2027, 23:59PM
Extension end date (if all the extensions are used): 31 August 2032
Can this contract be extended?: Yes
Renewal description:
The initial appointment covers the development phase of the Lymington Sea Water Baths Restoration Project, with completion of Phase 1 services scheduled for 31 August 2027.
The contract provides for continuation into subsequent project phases, subject to funding, satisfactory performance, project requirements and the necessary Council and National Lottery Heritage Fund approvals.
These may include further design development, preparation of a future major grant application and, if separately instructed, consultancy services during capital delivery.
Continuation is not automatic. The scope, programme and fees for subsequent services must be agreed, with written instruction and the necessary approvals before commencement.
The agreement provides professional day rates for necessary additional or extended services. The timing and duration of subsequent phases will depend on the outcome of the development work, future funding decisions and the approved project programme.
Does this contract include options?: Yes
Options description:
The contract includes optional architectural, engineering and cost consultancy services for subsequent phases of the Lymington Sea Water Baths Restoration Project, as specified in Annex A of the JCT Consultancy Agreement and the incorporated Commission Brief.
The optional services include:
- RIBA Stage 3 design development and associated technical, engineering and cost consultancy services.
- Support for a future National Lottery Heritage Fund major grant application.
- If separately instructed, capital delivery services including RIBA Stage 4 technical design and preparation of tender documentation.
- Contract administration, site inspections, technical oversight and contractor coordination.
- Handover, soft landings and defects period activities.
The requirement for these services will be determined by the findings of the current development phase, the progression of the restoration project, funding availability and the necessary Council and National Lottery Heritage Fund approvals.
Fees for optional services are to be agreed in writing before commencement, having regard to the consultant's submitted day rates, agreed scope, programme and resource requirements.
No optional services may commence or become payable without prior written instruction and the necessary approvals.
The contract also allows additional services within the scope of the project and consultant's competence under Clause 6.2.