Description of the contract
This contract comprises a single Works Contract which is more fully defined in the Employer’s Requirements and will include the following scope:
Site establishment;
Pre-demolition asbestos surveys of required buildings;
Decontamination/decommissioning and removal of any and ALL bulk or residual hazardous substances including ALL above ground asbestos and residual hazardous materials from the Site;
Soft strip and removal of all non-structural elements of all buildings to be demolished;
Pre-demolition structural survey of buildings to be demolished;
Disconnection of services for the buildings scheduled to be demolished
Protection of retained buildings or buildings to be demolished at later sections of the Works;
All temporary or permanent design works;
Supply of all information required to the satisfaction of the local planning authority to allow discharge of Contractor responsible planning conditions;
Demolition of all Site buildings (excluding those stated to be retained) including any suspended basement layers and plinths;
Removal of all materials including equipment and plant plinths and podiums back to structural concrete slabs levels;
Removal of all materials hazardous or otherwise from site with the exception of the retained brick and concrete;
Removal of underground storage tanks and associated below ground infrastructure at the former fuel dispensing area.
Retention of designated roads;
Protection of retained structures and services;
Removal of all above ground redundant services;
Ecological protection and mitigation measures;
Crushing of retained brick and concrete and on-site, utilising the resulting 6F2 granular fill for site levelling.
|