Description of the contract
The scheme consists of remedial works to Lock 21 of the Monmouthshire & Brecon canal.
The works include:
1) Construct temporary haul road to site and materials storage area
2) General clearance of vegetation from lock
3) Removal of existing bund and replacement with puddle clay dam.
4) Importing of pumps and draining of site.
5) Dredging and removal of detritus from lock basin.
6) Reclamation of stone work and repairs to basin of locks
7) Dismantling and cleaning of blockwork and rebuilding of lock basin
8) Removal and re-erection of stanking rails and boards
9) Construction of reinforced concrete slab in base of lock
10) Pressure grouting and repointing to lock walls and base
11) Erection of timber parapets and fencing
|