Capel Curig / Crafnant Bridleway Restoration |
+44 1766770274 |
adam.daniel@eryri.llyw.cymru |
|
| www.eryri.llyw.cymru |
|
1.3
|
Completed documents must be returned to:
Snowdonia National Park Authority/Awdurdod Parc Cenedlaethol Eryri |
Solicitor and Monitoring Officer, Solicitor and Monitoring Officer, Snowdonia National Park Authority, |
Penrhyndeudraeth |
LL48 6LF |
UK |
Capel Curig / Crafnant Bridleway Restoration |
+44 1766770274 |
iwan.jones@eryri.llyw.cymru |
|
| www.eryri.llyw.cymru |
|
2 Contract Details
|
2.1
|
Title
Capel Curig / Crafnant Bridleway Restoration
|
2.2
|
Description of the goods or services required
Scope of Works
The work specified within this tender is situated between Llyn Crafnant and the A5 trunk road at Capel Curig. The purpose of the work is to improve the existing R.O.W. infrastructure between the Ogwen and Conwy valleys and to significantly reduce the risk of further degradation and erosion of this fragile landscape.
The work will be undertaken in accordance with accepted and long-established good working practices. Construction techniques will be environmentally sound and will focus on sustainable construction, with minimal future maintenance costs. It is crucial that the paths have minimal visual impact on the landscape and should provide the user with an intimate experience of the surrounding area. The path should work with the terrain rather than working through it.
The construction will be of a solid surface technique (dictated by the terrain and underlying geology) with extensive sections of aggregate surfacing, and some sections requiring partial floating over soft terrain. Some sections will also require significant drainage management (to minimise impediment and maintain the natural flow) necessitating in the construction of cross culverting and ballast filled side drainage (approx. 90% of drainage construction will utilise the pre-existing and extensive ditching network to be found on site). Further works will include the replacement of gates.
NOTE: To register your interest in this notice and obtain any additional information please visit the Sell2Wales Web Site at https://www.sell2wales.gov.wales/Search/Search_Switch.aspx?ID=114697.
|
2.3
|
Notice Coding and Classification
|
|
|
|
|
45233161 |
|
Footpath construction work |
|
45233253 |
|
Surface work for footpaths |
|
45233340 |
|
Foundation work for footpaths |
|
|
|
|
|
1000 |
|
WALES |
|
1010 |
|
West Wales and The Valleys |
|
1011 |
|
Isle of Anglesey |
|
1012 |
|
Gwynedd |
|
1013 |
|
Conwy and Denbighshire |
|
1014 |
|
South West Wales (Carmarthenshire, Pembrokeshire, Ceredigion) |
|
1015 |
|
Central Valleys (Merthyr Tydfil, Rhondda Cynon Taf) |
|
1016 |
|
Gwent Valleys (Torfaen, Blaenau Gwent, Caerphilly) |
|
1017 |
|
Bridgend and Neath Port Talbot |
|
1018 |
|
Swansea |
|
1020 |
|
East Wales |
|
1021 |
|
Monmouthshire and Newport |
|
1022 |
|
Cardiff and Vale of Glamorgan |
|
1023 |
|
Flintshire and Wrexham |
|
1024 |
|
Powys |
|
2.4
|
Total quantity or scope of tender
The total length of bridleway to be repaired is approximately 2km.
The contractor will be expected to supply all materials, labour and machinery unless otherwise stated in the contract documents.
It is estimated that the contact duration will be approximately 5 months (dependant on site conditions, weather etc)
|
3 Conditions for Participation
|
3.1
|
Minimum standards and qualification required
Potential bidders should have a minimum of 5 years experience of this type of work, and should posess extensive evidence of previous similar work (photographs, testimonials etc.)
This is a weighted contract, the weighting being given as thus:-
Price 60%
Experience 40% (further split 60% rural / PROW work 40% H&S
record keeping - method statments, risk
assesments emergency site planning, pollution
mitigation and control etc.)
|
4 Administrative Information
|
4.1
|
Type of Procedure
Single stage
|
4.2
|
Reference number attributed to the notice by the contracting authority
N/a
|
4.3
|
Time LimitsTime-limit for receipt of completed tenders
15-10-2021
Time 12:00
Estimated award date 19-10-2021 |
4.5
|
Language or languages in which tenders or requests to participate can be drawn upEN
|
4.6
|
Tender Submission Postbox
|
5 Other Information
|
5.1
|
Additional Information
All relevant and additional information is contained within the contract document / scope of works.
If potential bidders should require further information this can be obtained by contacting the head of the Warden service, Adam Daniel on:-
07766 255 505
adam.daniel@eryri.llyw.cymru
(WA Ref:114697)
|
5.2
|
Additional Documentation
|
|
scope of works crafnant - FINAL 08102021 |
|
|
5.3
|