Contract Award Notice

Trecenydd Footbridge Refurbishment

  • First published: 13 August 2020
  • Last modified: 13 August 2020
  • Version: N/A
  •  

  • This file may not be fully accessible.

  •  

Information icon

The buyer is not using this website to administer the notice.

To record your interest or obtain additional information or documents please find instructions within the Full Notice Text. (NOTE: Contract Award Notices and Prior Information Notices do not normally require a response)

Contents

Summary

OCID:
ocds-kuma6s-101475
Published by:
Caerphilly County Borough Council
Authority ID:
AA0272
Publication date:
13 August 2020
Deadline date:
-
Notice type:
Contract Award Notice
Has documents:
No
Has SPD:
No
Has Carbon Reduction Plan:
N/A

Abstract

The work involved potential structural steel repairs, preparation to SA2 standard of cleanliness to bright steel and application of a three/two coat paint system over the entire footbridge and associated access steel ramps Remediation works will comprise either of the following Options individually or a combination of the two; Option 1: Footbridge remediation works as per the scope of works to be undertaken wholly in-situ of the bridge’s existing geographical location. Option 2: Footbridge remediation works to be undertaken in two part’s, simultaneously: Option 2: Part 1: Footbridge span, i.e structure spanning over traffic lanes, to be wholly removed and transported off site to a convenient location were the remediation works can be undertaken as per the scope of works. A site has been identified approximilty 1.5 miles east if the site, traveling eastward on the A469, see drawing SO901-006 for site location. Option 2: Part 2: Footbridge access ramps and steps to remain in-situ and remediation works undertaken within existing geographical location as per the scope of works. Working at height and management of traffic will be a specific hazard. Suitable temporary works such as design scaffolds (structural otherwise) will be required. Suitable planning and precaution required ensuring health and safety especially working at height and protection from hazardous processes of all who may be affected. If Option 2 is employed, suitably designed temporary structurers will be required to support cantilevering access ramps .The structural scaffolding will be designed to support the existing remaining structures and must be installed prior to lifting the main span. The contractor is to ensure any foundations and / or footing’s supporting the temporary works is suitable and satisfies the allowable ground bearing capacity. The loosening, lifting and transportation of the main span off site and subsequently returned and reconnecting must be undertaken and managed by a suitably qualified company and personal. A lifting plan must be developed and submitted for review / comment from the Client / Principal designer. All scaffolding, structural or otherwise, must be designed by a suitably competent designer who’s name and company must be supplied as part of the CPP. Additionally, calculations, design mythology and drawings ( if appropriate ) must be supplied to the Authority’s Principal Designer for review / comment prior to work commencement .CCBC will provide bridge loading / weight to inform any propping, transportation requirements. The appointed contractor or principal contractor are responsible for all temporary works design including water management and access. The contract is NEC3 Contract. This notice is to inform the market of a contract award

Full notice text

CONTRACT AWARD NOTICE – NATIONAL

WORKS

1 Authority Details

1.1

Authority Name and Address


Caerphilly County Borough Council

Infrastructure Division, Tredomen House, Tredomen Park, Ystrad Mynach,

Hengoed

CF82 7WF

UK

Jonathan Abraham

+44 1443866557

AbrahJ@caerphilly.gov.uk

+44 1443863167
www.caerphilly.gov.uk

2 Contract Details

2.1

Title

Trecenydd Footbridge Refurbishment

2.2

Description of the contract

The work involved potential structural steel repairs, preparation to SA2 standard of cleanliness to bright steel and application of a three/two coat paint system over the entire footbridge and associated access steel ramps

Remediation works will comprise either of the following Options individually or a combination of the two;

Option 1: Footbridge remediation works as per the scope of works to be undertaken wholly in-situ of the bridge’s existing geographical location.

Option 2: Footbridge remediation works to be undertaken in two part’s, simultaneously:

Option 2: Part 1: Footbridge span, i.e structure spanning over traffic lanes, to be wholly removed and transported off site to a convenient location were the remediation works can be undertaken as per the scope of works. A site has been identified approximilty 1.5 miles east if the site, traveling eastward on the A469, see drawing SO901-006 for site location.

Option 2: Part 2: Footbridge access ramps and steps to remain in-situ and remediation works undertaken within existing geographical location as per the scope of works.

Working at height and management of traffic will be a specific hazard. Suitable temporary works such as design scaffolds (structural otherwise) will be required. Suitable planning and precaution required ensuring health and safety especially working at height and protection from hazardous processes of all who may be affected.

If Option 2 is employed, suitably designed temporary structurers will be required to support cantilevering access ramps .The structural scaffolding will be designed to support the existing remaining structures and must be installed prior to lifting the main span. The contractor is to ensure any foundations and / or footing’s supporting the temporary works is suitable and satisfies the allowable ground bearing capacity. The loosening, lifting and transportation of the main span off site and subsequently returned and reconnecting must be undertaken and managed by a suitably qualified company and personal. A lifting plan must be developed and submitted for review / comment from the Client / Principal designer.

All scaffolding, structural or otherwise, must be designed by a suitably competent designer who’s name and company must be supplied as part of the CPP. Additionally, calculations, design mythology and drawings ( if appropriate ) must be supplied to the Authority’s Principal Designer for review / comment prior to work commencement .CCBC will provide bridge loading / weight to inform any propping, transportation requirements.

The appointed contractor or principal contractor are responsible for all temporary works design including water management and access.

The contract is NEC3 Contract.

This notice is to inform the market of a contract award

2.3

Notice Coding and Classification

45220000 Engineering works and construction works
45442121 Painting work of structures
1016 Gwent Valleys (Torfaen, Blaenau Gwent, Caerphilly)

2.4

Estimated Total Value

3 Procedure

3.1

Type of Procedure

Single stage

4 Award of Contract

4.1

Successful Bidders

4.1.1

Name and Address of successful supplier, contractor or service provider





Beaver Bridges Limited

5 Knights Court, Archers Way, Battlefield Enterprise Park,

Shrewsbury

SY13GA

UK




www.beaverbridges.co.uk

5 Other Information

5.1

Reference number attributed to the notice by the contracting authority

SO901

5.2

Date of Contract Award

 11-06-2020

5.3

Number of tenders received

3

5.4

Other Information

(WA Ref:103456)

5.5

Additional Documentation

N/a

5.6

Publication date of this notice:

 13-08-2020

Coding

Commodity categories

ID Title Parent category
45220000 Engineering works and construction works Works for complete or part construction and civil engineering work
45442121 Painting work of structures Application work of protective coatings

Delivery locations

ID Description
1016 Gwent Valleys (Torfaen, Blaenau Gwent, Caerphilly)

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

Document family

Notice details
Publication date:
24 April 2020
Deadline date:
29 May 2020 00:00
Notice type:
Contract Notice
Authority name:
Caerphilly County Borough Council
Publication date:
13 August 2020
Notice type:
Contract Award Notice
Authority name:
Caerphilly County Borough Council

About the buyer

Main contact:
AbrahJ@caerphilly.gov.uk
Admin contact:
N/a
Technical contact:
N/a
Other contact:
N/a

Further information

Date Details
No further information has been uploaded.

0800 222 9004

Lines are open 8:30am to 5pm Monday to Friday.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.